Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2020 (5) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (5) TMI 242 - SC - Indian Laws


Issues Involved:
1. Interpretation of Clause 23 of the contract.
2. Scope of judicial review under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996.
3. The applicability of the "force majeure" clause and the doctrine of frustration.
4. Whether the arbitral award was against the public policy of India.

Detailed Analysis:

1. Interpretation of Clause 23 of the contract:

The core issue revolves around the interpretation of Clause 23, which deals with subsequent changes in law affecting the contract. The Arbitral Tribunal interpreted Clause 23 to include changes in the price of High-Speed Diesel (HSD) as a "change in law," arguing that even government circulars have the "force of law." The Tribunal applied a "liberal interpretation rule" to include price changes under Clause 23, terming it a "Habendum Clause," which should be construed broadly to include government orders and instructions.

Conversely, the High Court held that Clause 23 was akin to a "force majeure" clause, meant to address unforeseen events that make contract performance impossible. The High Court argued that Clause 23 was not intended for revising fixed contract rates but to address changes in law that would make the contract impossible to perform.

2. Scope of judicial review under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996:

The High Court set aside the arbitral award under Section 37, stating that the Arbitral Tribunal's interpretation was erroneous and against the public policy of India. The Supreme Court examined the scope of judicial review under Section 34, emphasizing that an arbitral award should not be interfered with unless it is patently illegal or against public policy. The Court cited Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd., emphasizing that arbitral awards should not be interfered with casually and that the courts should respect the finality of the arbitral process.

3. The applicability of the "force majeure" clause and the doctrine of frustration:

The High Court equated Clause 23 with a "force majeure" clause, which under Indian law, discharges parties from future obligations if an unforeseen event makes performance impossible. The Supreme Court discussed the doctrine of frustration under Section 56 of the Indian Contract Act, 1872, which voids contracts that become impossible to perform due to unforeseen events. The Court clarified that Clause 23 was not intended to address price fluctuations but to mitigate risks associated with changes in law that would make the contract impossible to perform.

4. Whether the arbitral award was against the public policy of India:

The Supreme Court concluded that the Arbitral Tribunal's interpretation of Clause 23 to include changes in HSD prices was not a possible interpretation of the contract. The Court emphasized that the contract was based on a fixed rate, and price fluctuations were foreseeable risks that the contractor should have accounted for. The Tribunal's interpretation was deemed perverse as it ignored the explicit terms of the contract, which required the contractor to bear the cost of fuel.

Conclusion:

The Supreme Court upheld the High Court's decision to set aside the arbitral award, finding that the Arbitral Tribunal's interpretation of Clause 23 was unreasonable and not supported by the contract's terms. The appeal was dismissed, and the judgment emphasized the importance of adhering to the explicit terms of the contract and the limited scope of judicial review in arbitral matters.

 

 

 

 

Quick Updates:Latest Updates