Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2020 (11) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (11) TMI 189 - SC - Indian Laws


Issues Involved:
1. Jurisdiction of the Consumer Protection Act (CP Act) vis-à-vis the Real Estate (Regulation and Development) Act (RERA Act).
2. Definition of "Consumer" under the CP Act.
3. Delay in the completion of the housing project.
4. Force majeure and its applicability.
5. Remedies available to the allottees under the CP Act and RERA Act.
6. Validity of the National Consumer Disputes Redressal Commission (NCDRC) order.

Detailed Analysis:

1. Jurisdiction of the CP Act vis-à-vis the RERA Act:
The Supreme Court analyzed whether the remedies available under the CP Act would be additional remedies over and above those provided under the RERA Act. It was concluded that the CP Act provides additional remedies and the availability of an alternative remedy does not bar the entertaining of a complaint under the CP Act. The Court referred to Section 88 of the RERA Act, which states that its provisions are in addition to and not in derogation of any other law. The Court emphasized that the RERA Act does not bar the jurisdiction of the Consumer Fora under the CP Act, even after the RERA Act came into force.

2. Definition of "Consumer" under the CP Act:
The Court upheld the NCDRC’s conclusion that the complainants were "Consumers" within the meaning of the CP Act. The complainants had purchased the apartments for self-use, and not for commercial purposes, which qualified them as consumers under Section 2(d) of the CP Act.

3. Delay in the Completion of the Housing Project:
The NCDRC found that there was a significant delay in the completion of the project, which was not justified by the developer. The Supreme Court agreed with this finding, noting that the developer had acknowledged the delay but attempted to justify it with reasons such as demonetization and labor shortages, which were not accepted as valid force majeure events.

4. Force Majeure and its Applicability:
The Court rejected the developer’s argument that events such as demonetization and labor shortages constituted force majeure. It was noted that the developer failed to provide evidence supporting these claims. The NCDRC correctly concluded that these events did not qualify as force majeure under the terms of the Builder Buyer Agreement.

5. Remedies Available to the Allottees under the CP Act and RERA Act:
The Supreme Court confirmed that the remedies under the CP Act are additional to those under the RERA Act. Section 18 of the RERA Act provides remedies for allottees who wish to withdraw from the project or seek compensation for delays. However, the CP Act also offers a parallel remedy, allowing consumers to seek redressal under both statutes.

6. Validity of the NCDRC Order:
The Supreme Court upheld the NCDRC’s order, which directed the developer to refund the amounts deposited by the complainants with simple interest at 9% per annum from the respective dates of deposits till realization, along with costs of ?50,000 to each complainant. The Court found no merit in the developer’s arguments against the NCDRC’s jurisdiction and the applicability of the RERA Act.

Conclusion:
The Supreme Court dismissed the appeals, affirming the NCDRC’s decision. It was held that the remedies under the CP Act are in addition to those under the RERA Act, and the complainants were rightly considered consumers under the CP Act. The developer was ordered to comply with the NCDRC’s directions and pay additional costs of ?50,000 per consumer case.

 

 

 

 

Quick Updates:Latest Updates