Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2021 (12) TMI SC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (12) TMI 614 - SC - Indian Laws


Issues Involved:
1. Whether the arbitral award was in excess of the claim.
2. Whether the Arbitrator exceeded the scope of reference.
3. Whether the Arbitrator rewrote the contract with respect to the amount payable specified in the contract.

Detailed Analysis:

1. Excess of Claim:
The appellant contended that the arbitral award was in excess of the claim. The contractor had claimed ?1,03,50,263 under claim Nos. 1 and 8, but the Arbitrator awarded ?1,51,95,400, which was argued to be far in excess of the amount claimed. The appellant cited the decision in ONGC Ltd. v. OffShore Enterprises Inc. to support this contention. However, the respondent argued that the statement of claim specified that the amount of ?1,03,50,263 was worked out up to May 2007, and additional details would be submitted during the hearing. The court agreed with the respondent, noting that the claim was not restricted to ?1,03,50,263 and thus, the award was not in excess of the claim.

2. Scope of Reference:
The appellant argued that the Arbitrator exceeded the scope of reference by awarding an amount for a period beyond the date of entering reference (19.05.2007). They contended that the Arbitrator should have restricted the claim to either 06.03.2006 (date of invoking arbitration) or 23.04.2007 (date of appointing the Arbitrator). The appellant cited cases like Indian Aluminium Cables Ltd. v. Haryana State Electricity Board and MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr. to support their argument. However, the court found that the claim was justified till the traffic was diverted, which was up to January 2008, and thus, the Arbitrator did not exceed the scope of reference.

3. Rewriting the Contract:
The appellant contended that the Arbitrator rewrote the contract by awarding compensation at ?45,000 per km per month instead of the mutually agreed rate of ?1,000 per km per month. They argued that this was beyond the terms of the contract. The respondent countered that the additional expenditure was due to the increased traffic from the diversion, which was not anticipated in the original contract. The court agreed with the respondent, stating that the additional expenditure was justified due to the unforeseen increase in traffic, and thus, it was not a case of rewriting the contract.

Separate Judgments:
The court partially allowed the appeals, confirming the award of ?45,000 per km per month up to January 2008 but quashing the award for the period from February 2008 to 31.05.2010. The amount due was to be recalculated accordingly. There were no separate judgments delivered by the judges in this case.

 

 

 

 

Quick Updates:Latest Updates