Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases VAT and Sales Tax VAT and Sales Tax + HC VAT and Sales Tax - 2022 (5) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2022 (5) TMI 308 - HC - VAT and Sales Tax


Issues Involved:
1. Entitlement to exemption from payment of electricity duty for a 30 MW Captive Power Generation Plant under Clause 15.2.2 of the Jharkhand Industrial Policy-2001.
2. Validity and applicability of follow-up notifications extending the period of exemption.
3. Alleged concealment of material facts by the petitioner.
4. Interpretation of the terms "Industrial Unit" and "Captive Power Generation Plant" under the Industrial Policy.

Issue-wise Detailed Analysis:

1. Entitlement to Exemption from Payment of Electricity Duty:
The petitioner, a company with several industrial units in Jharkhand, established a 30 MW Captive Power Generation Plant (CPP) with a commercial production date of 4th May 2009. The primary issue was whether this plant was entitled to a ten-year exemption from electricity duty under Clause 15.2.2 of the Jharkhand Industrial Policy-2001. The court noted that the Industrial Policy aimed to encourage the establishment of CPPs to meet the power demands of industrial units. Clause 15.2.2 explicitly provided for a ten-year exemption from electricity duty for CPPs. The court found that the policy did not limit the exemption to only one CPP per industrial unit, and thus, the petitioner was entitled to the exemption for its 30 MW CPP.

2. Validity and Applicability of Follow-up Notifications:
The court addressed the issue of whether the follow-up notification (S.O. 70 dated 17.07.2004) limited the exemption to CPPs established between 15.11.2000 and 31.03.2005. The Industrial Policy was extended until 31.03.2011, but the follow-up notification was not amended accordingly until 26.03.2015. The court held that the delay in issuing the amended notification could not deprive the petitioner of its legitimate entitlement to the exemption. The court emphasized that the State's failure to timely update the notification was an arbitrary act that violated the doctrine of promissory estoppel and legitimate expectation.

3. Alleged Concealment of Material Facts:
The Commercial Taxes Tribunal had dismissed the petitioner's revision applications, partly on the grounds of alleged concealment of material facts, specifically the Business Transfer Agreement with Tata Steel Limited. The court found this finding to be perverse, as the State had not raised any objections regarding the transfer, and the tax liabilities remained with the petitioner. The court held that the Tribunal had exceeded its jurisdiction by dismissing the revision applications on this basis.

4. Interpretation of "Industrial Unit" and "Captive Power Generation Plant":
The State argued that the policy's incentives were only available once to an industrial unit and contended that the 10 MW and 30 MW CPPs were expansions of the existing 25 MW CPP. The court rejected this argument, noting that the policy treated CPPs and industrial units as distinct entities. Clause 15.2.2 did not restrict the number of CPPs that could be established by an industrial unit. The court also clarified that the definition of "Expansion/Modernization/Diversification" applied to industrial units, not CPPs.

Conclusion:
The court concluded that the petitioner was entitled to the benefit of exemption from electricity duty for its 30 MW CPP under Clause 15.2.2 of the Jharkhand Industrial Policy-2001. The orders of the Commercial Taxes Tribunal were quashed, and the matter was remanded to the Deputy Commissioner of Commercial Taxes to pass fresh assessment orders extending the benefit of exemption and issue consequential excess demand notices for refund of any realized electricity duty.

 

 

 

 

Quick Updates:Latest Updates