Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Central Excise Central Excise + AT Central Excise - 2023 (9) TMI AT This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2023 (9) TMI 176 - AT - Central Excise


Issues Involved:
1. Denial of SSI exemption by clubbing clearances of two entities.
2. Rejection of refund claims on grounds of limitation and unjust enrichment.
3. Entitlement to interest on delayed refund claims.

Summary:

Issue 1: Denial of SSI Exemption by Clubbing Clearances
The appellants, M/s Gillooram Gaurishankar and M/s G.P. Dalmia & Sons, were engaged in manufacturing electrical conductors and were registered as Small Scale Manufacturers under SSI exemption Notification No.175/86-CX dated 01.03.1986. The Central Excise Authorities denied the SSI exemption by clubbing the clearances of both entities, arguing that the proprietor of M/s G.P. Dalmia & Sons was also a partner in M/s Gillooram Gaurishankar. This clubbing pushed the clearances beyond the exemption limit. However, the Tribunal, in its orders dated 06.10.1986, 15.12.1986, and 25.10.1989, held that both entities were distinct for the purposes of the Central Excise Act and could not be treated as a single entity.

Issue 2: Rejection of Refund Claims on Grounds of Limitation and Unjust Enrichment
Following the Tribunal's orders, the appellants filed refund claims for the duty paid under protest. Various show-cause notices were issued to deny these refund claims on the grounds of limitation and non-compliance with Rule 233B of the Central Excise Rules, 1944. The Commissioner (Appeals) set aside these objections, ruling that the duty was indeed paid under protest, and remanded the case for fresh adjudication. However, the Assistant Collector rejected the refund claims again, this time on the grounds of unjust enrichment. The appellants challenged this, arguing that the concept of unjust enrichment was introduced only in 1991 and should not apply to their earlier claims. They also contended that no show-cause notice regarding unjust enrichment was issued, violating the procedural requirements as per CBEC Circular No.19/93-CX-6 dated 29.12.1993.

Issue 3: Entitlement to Interest on Delayed Refund Claims
The Tribunal found that the appellants had not collected any duty from Bihar State Electricity Board, to whom the clearances were made, and thus had borne the duty themselves. The Tribunal held that the appellants had passed the bar of unjust enrichment and were entitled to the refund. Additionally, the Tribunal ruled that the appellants were entitled to interest on the delayed refund claims from the date of filing the refund claim till realization, citing the Supreme Court's decision in Ranbaxy Laboratories Limited Vs. Union of India, which mandates interest payment from three months after the refund claim application date. The Tribunal set the interest rate at 12%, referencing its own decisions and those of other benches.

Conclusion:
The Tribunal allowed all the appeals with consequential relief, including the refund of the duty paid under protest and interest at the rate of 12% per annum from three months after the filing of the refund claims until their realization.

 

 

 

 

Quick Updates:Latest Updates