Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2023 (10) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2023 (10) TMI 417 - HC - Indian Laws


Issues Involved:
1. Claim No. 2: Extra cost due to prolongation of the contract.
2. Claim No. 3: Additional cost due to the use of a 4-bolt fastening system.
3. Claim No. 4: Abnormal increase in the quantity of track fastenings.
4. Claim No. 12: Additional GST burden.

Summary:

Claim No. 2: Extra Cost Due to Prolongation of the Contract
The Contractor sought compensation for extra costs incurred due to the 18-month delay in project completion, attributing the delay to DMRC. The Arbitral Tribunal (AT) partially allowed sub-claims 2(a), (b), and (c) but rejected sub-claims 2(d) and (e), citing lack of cogent evidence. The AT relied on Clause 8.3 of the General Conditions of Contract (GCC) and noted that the Contractor had reserved the right to seek compensation only during the third extension of time (EOT). Therefore, compensation was awarded only for the six-month period from 01.01.2018 to 30.06.2018.

Claim No. 3: Additional Cost Due to Use of 4-Bolt Fastening System
The Contractor claimed additional costs due to a change in design, which required the use of a 4-bolt fastening system. The AT rejected this claim, stating that the Bill of Quantities (BOQ) was based on the radius of the curve rather than the number of bolts. The AT observed that the Contractor did not object to the design changes at the time and failed to link the design change to the increased number of bolts.

Claim No. 4: Abnormal Increase in Quantity of Track Fastenings
Similar to Claim No. 3, the Contractor claimed costs due to an abnormal increase in the quantity of track fastenings. The AT rejected this claim, noting that the BOQ specified quantities based on the radius of the curve and not on the number of bolts. The AT found no evidence that the increase in bolts was due to design changes required by DMRC.

Claim No. 12: Additional GST Burden
The Contractor claimed compensation for the additional GST burden. The AT partially allowed this claim, awarding Rs. 26,44,277/- towards the additional GST burden at 1.40%, as initially agreed by DMRC. The AT noted that the Contractor failed to substantiate the amount of input credit availed and relied on Clause 27(v) of the Special Conditions of Contract (SCC), which restricted adjustments in contract price due to changes in taxes.

Conclusion:
The court dismissed the petition, finding no "patent illegality" in the AT's award. The court emphasized that it is not within its jurisdiction to reappreciate evidence or correct legal errors made by the AT. The AT's interpretations and findings were deemed plausible and judicially appropriate.

 

 

 

 

Quick Updates:Latest Updates