Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 1999 (9) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

1999 (9) TMI 770 - SC - Indian Laws


Issues Involved:
1. Jurisdiction of the arbitrator.
2. Interpretation and application of contract clauses 17 and 18.
3. Validity of claims for escalation and additional costs.
4. Admissibility of claims under the arbitration agreement.
5. Conduct and decision-making process of the arbitrator.

Issue-wise Detailed Analysis:

1. Jurisdiction of the Arbitrator:
The Supreme Court examined whether the arbitrator exceeded his jurisdiction by awarding claims that were explicitly barred by the contract. The court noted that the arbitrator's authority was derived from the agreement dated 14-05-1981, which clearly stipulated fixed rates and barred escalation claims. The arbitrator, by ignoring these stipulations, acted beyond his jurisdiction. The court emphasized that the arbitrator is bound by the terms of the contract and cannot award amounts prohibited by it.

2. Interpretation and Application of Contract Clauses 17 and 18:
Clauses 17 and 18 of the contract explicitly stated that the contractor would be paid a fixed rate of Rs. 35.80 per cubic meter and would not be entitled to any additional payments for escalation or increased costs. These clauses were clear and unambiguous, leaving no room for interpretation. The arbitrator's award, which granted additional payments for increased costs and escalation, was in direct violation of these clauses. The court held that the arbitrator's decision to ignore these clauses constituted a deliberate departure from the contract, amounting to a jurisdictional error.

3. Validity of Claims for Escalation and Additional Costs:
The contractor's claims for increased rates due to unforeseen conditions, use of high explosives, non-availability of explosives, and additional costs for mining and transportation were explicitly barred by the contract. The court noted that the contract was signed with the understanding that the rates were firm and final, with no provision for escalation except for diesel costs. The arbitrator's award granting these claims was therefore invalid and beyond the scope of his jurisdiction.

4. Admissibility of Claims Under the Arbitration Agreement:
The arbitration clause in the contract was broadly worded, covering all disputes arising out of or in any way touching or concerning the contract. However, the court clarified that this broad wording did not empower the arbitrator to ignore specific prohibitions in the contract. The arbitrator could not award claims that were explicitly barred by the contract, even if the arbitration clause was wide. The court held that the arbitrator's award was in excess of his jurisdiction because it disregarded the specific terms of the contract.

5. Conduct and Decision-Making Process of the Arbitrator:
The court found that the arbitrator had acted improperly by ignoring the clear and unambiguous terms of the contract. This constituted a manifest disregard of his authority and amounted to misconduct. The arbitrator's award was also criticized for being non-speaking, i.e., it did not provide reasons for granting the claims. The court reiterated that an arbitrator must operate within the limits set by the contract and cannot act arbitrarily or capriciously.

Conclusion:
The Supreme Court quashed and set aside the arbitrator's award, as well as the judgments of the High Court and the District Judge, Udaipur, which had upheld the award. The court emphasized that the arbitrator had exceeded his jurisdiction by ignoring the specific terms of the contract, which clearly barred the claims awarded. The appeal was allowed with costs, and the award was declared invalid.

 

 

 

 

Quick Updates:Latest Updates