Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2014 (2) TMI SC This

  • Login
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2014 (2) TMI 1252 - SC - Indian Laws


Issues Involved:
1. Validity of the High Court's appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.
2. Interpretation and modification of Clause 25 of the original contract by supplementary agreements.
3. Determination of the appropriate arbitration mechanism between the appellant and the respondent.
4. Equitable resolution of disputes and claims between the parties.

Issue-wise Detailed Analysis:

1. Validity of the High Court's Appointment of an Arbitrator:
The High Court appointed an arbitrator on behalf of the appellant under Section 11(6) of the Arbitration and Conciliation Act, 1996, due to the appellant's failure to nominate its arbitrator as per Clause 25 of the original agreement. The appellant contested this appointment, arguing that Clause 25 had been modified by supplementary agreements, negating the need for arbitration at this stage. The Supreme Court found that the High Court erred in its decision, as Clause 25 had indeed been materially altered by the supplementary agreements, thus invalidating the High Court's appointment of an arbitrator.

2. Interpretation and Modification of Clause 25:
Clause 25 of the original agreement provided for arbitration to settle disputes between the appellant and the respondent. However, this clause was significantly modified by three supplementary agreements. The first supplementary agreement (dated 31.1.1990) established that disputes involving the respondent's work would be treated as joint disputes between the appellant and SCOPE, to be settled through negotiation or arbitration with SCOPE. The second supplementary agreement (dated 8.12.1993) reinforced this mechanism, stating that no arbitration would occur between the appellant and the respondent regarding these claims until the project's completion. The third supplementary agreement (dated 6.2.1995) further confirmed this approach and specified that any arbitration would follow the modified terms of the first supplementary agreement.

3. Determination of the Appropriate Arbitration Mechanism:
The modified arbitration mechanism required the appellant to raise the respondent's claims with SCOPE, with the respondent's assistance and cooperation. Only if disputes remained unresolved after arbitration with SCOPE could arbitration occur between the appellant and the respondent. The Supreme Court emphasized that the modified Clause 25 did not permit the respondent to unilaterally seek arbitration with the appellant at this stage, as the claims first had to be addressed through the joint mechanism with SCOPE.

4. Equitable Resolution of Disputes and Claims:
The Supreme Court acknowledged the respondent's frustration with delays but emphasized that the contractual agreements between the parties must be honored. The Court directed the appellant to ensure that SCOPE settled the final bill within two months. If disputes remained after SCOPE's settlement, the appellant was to invoke arbitration with SCOPE, with the respondent's cooperation. If the appellant chose not to pursue arbitration with SCOPE but the respondent still had legitimate claims, arbitration between the appellant and the respondent would proceed under Clause 25. The arbitral tribunal was instructed to render its award within six months of its constitution.

Conclusion:
The Supreme Court allowed the appeal, setting aside the High Court's order and providing clear directions to expedite the resolution of disputes through the agreed arbitration mechanisms. The judgment emphasized adherence to the modified contractual terms and aimed to balance the equities between the parties.

 

 

 

 

Quick Updates:Latest Updates