Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2011 (4) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2011 (4) TMI 1467 - SC - Indian Laws


Issues Involved:
1. Whether the High Court was justified in setting aside the award in respect of claims 1, 3, and 11 on the ground that they related to 'excepted matters'.
2. Whether the High Court was justified in setting aside the award in regard to Claim Nos. 2, 4, 6, 7, 8, and 9.
3. Whether the High Court was justified in holding that claim 5 for escalation was barred by Clause 10(cc) of the contract.
4. Whether the High Court was justified in setting aside the award rejecting counter-claims 1 to 4.

Detailed Analysis:

Issue 1: Claims 1, 3, and 11 as 'Excepted Matters'
The High Court held that claims 1, 3, and 11 were not arbitrable as they related to excepted matters where the decisions of the Superintending Engineer or Engineer-in-Charge were final and binding under Clauses (2) and (3) of the agreement. However, the Supreme Court analyzed the relevant clauses and found that:
- Clause (2) made the decision of the Superintending Engineer final only in regard to the percentage of compensation for delay, not on the responsibility for the delay.
- Clause (3) made the Engineer-in-Charge's decision final only in regard to the potential inability to complete the work by the due date, not on the reasons for the delay or the validity of termination.
- The Supreme Court concluded that the decision on who was responsible for the delay was arbitrable and upheld the arbitrator's finding that the Respondents were responsible for the delay and the termination was illegal. Thus, the award on claims 1, 3, and 11 was upheld, and the High Court's conclusion was set aside.

Issue 2: Setting Aside Awards on Claims 2, 4, 6, 7, 8, and 9
The High Court set aside these claims on the ground that if counter-claims 1 to 4 were allowed, Respondents would be entitled to adjust the amounts awarded. The Supreme Court noted that:
- The awards on claims 2, 4, 6, 7, 8, and 9 were upheld by the civil court and the High Court did not find any infirmity in them.
- The Supreme Court held that if an award deals with several claims separately and distinctly, the court should segregate and uphold the award on items that do not suffer from any infirmity.
- Therefore, the judgment of the High Court setting aside these claims was unsustainable, and the award on claims 2, 4, 6, 7, 8, and 9 was upheld.

Issue 3: Claim 5 and Clause 10(cc) of the Contract
The High Court set aside the award on claim 5, holding that it violated Clause 10(cc) of the contract. The Supreme Court found that:
- Clause 10(cc) allowed for escalation in prices only for work done during the stipulated period or validly extended period without any action under Clause 2.
- The arbitrator found that the contractor was not responsible for the delay and was entitled to a valid extension without penalty.
- The Supreme Court concluded that the contractor was entitled to escalation for the work done from 1.8.1995 to 14.3.1996, and the High Court erred in setting aside the award on claim 5.

Issue 4: Rejection of Counter-Claims 1 to 4
The High Court assumed that Clauses (2) and (3) made the decisions on liability to pay liquidated damages and extra costs final and inarbitrable. The Supreme Court held that:
- The arbitrator's findings that the contractor was not responsible for the delay and the termination was wrongful were not open to challenge.
- Consequently, the Respondents were not entitled to claim extra costs or levy liquidated damages.
- The rejection of the counter-claims by the arbitrator was upheld, and the High Court's finding was unsustainable.

Conclusion:
The Supreme Court allowed the appeal, set aside the impugned order of the High Court, and restored the order of the District Court dated 12.12.2003.

 

 

 

 

Quick Updates:Latest Updates