Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2017 (2) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2017 (2) TMI 1322 - SC - Indian Laws


Issues involved:
1. Legality of sub-contracting between the parties.
2. Disputes regarding payments for executed work.
3. Applicability of revised rates in the sub-contract.
4. Jurisdiction and authority of the arbitrator.
5. High Court's authority to interfere with the arbitrator's award.

Issue-wise detailed analysis:

1. Legality of sub-contracting between the parties:
The National Hydro-Electric Power Corporation Ltd. (NHPC) awarded a contract to Hindustan Steel Works Construction Ltd. (HSCL) for construction work. HSCL sub-contracted the work to Progressive Construction Ltd. (PCL), which further sub-contracted it to M/s. Sharma & Associates Contractors (P) Ltd. (SAPL). It was admitted that sub-contracting by PCL to SAPL was not permissible.

2. Disputes regarding payments for executed work:
Disputes arose between SAPL and PCL over unpaid amounts for executed work. These disputes were referred to arbitration as per the arbitration clause in the contract between SAPL and PCL. The arbitrator awarded a sum of ?19,38,357/- to SAPL for Claim No. 1, which was upheld by the learned Single Judge.

3. Applicability of revised rates in the sub-contract:
The core of Claim No. 1 was whether SAPL was entitled to revised rates received by PCL from HSCL for deviations in quantities. SAPL argued that it was a back-to-back contract, and thus, the revised rates should apply. The arbitrator accepted this plea, but the Division Bench of the High Court disagreed, holding that the contract between SAPL and PCL was independent and did not incorporate terms from the HSCL-PCL contract.

4. Jurisdiction and authority of the arbitrator:
The Division Bench found that the arbitrator erred by relying on terms from the HSCL-PCL contract, which were not applicable to the SAPL-PCL contract. The High Court noted that the arbitrator's approach was fundamentally flawed, as it was based on provisions not incorporated into the SAPL-PCL contract. The High Court emphasized that the arbitrator must adhere to the specific terms of the contract between the parties.

5. High Court's authority to interfere with the arbitrator's award:
The High Court held that it was within its jurisdiction to correct the arbitrator's fundamental error. The court cited precedents stating that an arbitrator is bound by the contract terms and cannot ignore them to achieve what he thinks is just and reasonable. The High Court concluded that the arbitrator's award was based on a jurisdictional error, as it relied on terms not applicable to the SAPL-PCL contract.

Conclusion:
The appeal was dismissed, affirming the High Court's decision that the arbitrator's award was based on an incorrect application of contract terms. The High Court's interference was justified as it addressed a fundamental jurisdictional issue, ensuring that the arbitrator adhered strictly to the contract between SAPL and PCL.

 

 

 

 

Quick Updates:Latest Updates