2011 (4) TMI 489 - SC - FEMA


  1. 2023 (10) TMI 1208 - SC
  2. 2022 (2) TMI 1219 - SC
  3. 2021 (9) TMI 1155 - SC
  4. 2021 (1) TMI 802 - SC
  5. 2019 (2) TMI 1043 - SC
  6. 2018 (10) TMI 777 - SC
  7. 2015 (9) TMI 780 - SC
  8. 2015 (5) TMI 214 - SC
  9. 2015 (4) TMI 849 - SC
  10. 2015 (2) TMI 735 - SC
  11. 2015 (1) TMI 929 - SC
  12. 2013 (3) TMI 518 - SC
  13. 2023 (7) TMI 636 - HC
  14. 2022 (11) TMI 1233 - HC
  15. 2022 (7) TMI 420 - HC
  16. 2022 (5) TMI 262 - HC
  17. 2021 (9) TMI 156 - HC
  18. 2020 (5) TMI 225 - HC
  19. 2019 (11) TMI 278 - HC
  20. 2019 (5) TMI 1178 - HC
  21. 2019 (5) TMI 321 - HC
  22. 2019 (4) TMI 1248 - HC
  23. 2019 (6) TMI 746 - HC
  24. 2018 (2) TMI 1757 - HC
  25. 2017 (10) TMI 691 - HC
  26. 2017 (2) TMI 82 - HC
  27. 2017 (1) TMI 1810 - HC
  28. 2016 (12) TMI 1747 - HC
  29. 2016 (10) TMI 1388 - HC
  30. 2016 (11) TMI 1071 - HC
  31. 2016 (8) TMI 1255 - HC
  32. 2016 (2) TMI 414 - HC
  33. 2015 (5) TMI 939 - HC
  34. 2014 (12) TMI 1348 - HC
  35. 2015 (2) TMI 296 - HC
  36. 2014 (7) TMI 727 - HC
  37. 2014 (8) TMI 225 - HC
  38. 2014 (4) TMI 466 - HC
  39. 2014 (4) TMI 612 - HC
  40. 2015 (9) TMI 1327 - HC
  41. 2014 (1) TMI 1223 - HC
  42. 2015 (9) TMI 338 - HC
  43. 2013 (12) TMI 1278 - HC
  44. 2013 (1) TMI 128 - HC
  45. 2012 (7) TMI 641 - HC
  46. 2012 (6) TMI 37 - HC
  47. 2012 (5) TMI 378 - HC
  48. 2012 (2) TMI 177 - HC
  49. 2013 (11) TMI 16 - HC
  50. 2023 (11) TMI 100 - AT
  51. 2023 (12) TMI 11 - AT
  52. 2023 (9) TMI 711 - AT
  53. 2022 (5) TMI 1548 - AT
  54. 2021 (12) TMI 580 - AT
  55. 2021 (8) TMI 775 - AT
  56. 2021 (1) TMI 1035 - AT
  57. 2020 (10) TMI 836 - AT
  58. 2020 (10) TMI 547 - AT
  59. 2020 (7) TMI 643 - AT
  60. 2020 (1) TMI 772 - AT
  61. 2019 (11) TMI 1025 - AT
  62. 2019 (3) TMI 1820 - AT
  63. 2019 (4) TMI 1185 - AT
  64. 2018 (11) TMI 622 - AT
  65. 2018 (10) TMI 1081 - AT
  66. 2018 (7) TMI 1964 - AT
  67. 2018 (3) TMI 1291 - AT
  68. 2018 (3) TMI 1066 - AT
  69. 2017 (8) TMI 409 - AT
  70. 2017 (5) TMI 1303 - AT
  71. 2016 (7) TMI 424 - AT
  72. 2014 (1) TMI 1642 - AT
  73. 2012 (8) TMI 498 - AT
  74. 2018 (12) TMI 1125 - Tri
  75. 2021 (1) TMI 1009 - NAPA
  76. 2020 (3) TMI 558 - NAPA
  77. 2013 (9) TMI 1270 - Board
Issues Involved:
1. Whether the Appellate Tribunal under FEMA was correct in rejecting a belated appeal by applying the limitation period from FERA.
2. Whether the Tribunal had the power to condone the delay beyond the 90-day period prescribed by FERA.
3. Whether the High Court could entertain writ petitions under Article 226 of the Constitution of India when the Tribunal dismissed the appeal for delay.
4. The applicability of procedural and substantive law concerning the appeal process under FEMA and FERA.
5. The impact of the repealing and saving clause of FEMA on the right of appeal.

Detailed Analysis:

1. Applicability of FERA or FEMA for Limitation Period:
The primary issue was whether the limitation period for filing an appeal should be governed by the first proviso to sub-section (2) of Section 52 of FERA or the proviso to sub-section (2) of Section 19 of FEMA. The Court noted that the cause of action arose under FERA, but the show cause notices and orders were issued after FEMA came into force. The appeals were filed under sub-section (1) of Section 19 of FEMA. The Court clarified that procedural law, including limitation periods, operates retrospectively unless it adversely affects vested rights. Thus, the limitation for filing the appeal should be considered under the proviso to sub-section (2) of Section 19 of FEMA.

2. Tribunal's Power to Condon Delay:
The Tribunal dismissed the appeals on the ground of delay, stating it had no power to condone delays beyond 90 days as per FERA. However, the Court held that the proviso to sub-section (2) of Section 19 of FEMA, which allows the Tribunal to entertain appeals filed after 45 days if sufficient cause is shown, should apply. Unlike FERA, FEMA does not impose a ceiling on the period of delay that can be condoned. Therefore, the Tribunal was empowered to condone the delay if sufficient cause was demonstrated.

3. High Court's Jurisdiction under Article 226:
The High Court dismissed the writ petitions, stating it would not be appropriate to entertain them as petitions against the original order. The Court emphasized that the High Court has the power to exercise its extraordinary jurisdiction under Article 226 of the Constitution of India, especially when the impugned order of the Tribunal was manifestly illegal. The High Court could have condoned the delay and directed the Tribunal to consider the appeal on merits.

4. Substantive and Procedural Law:
The Court elaborated on the distinction between substantive and procedural law. The right to appeal is a substantive right, while the procedure for filing an appeal, including the period of limitation, is procedural. Procedural law is retrospective, meaning it applies to all actions after its enactment, even if the cause of action arose under a repealed statute. The Court cited several precedents to support this interpretation, emphasizing that procedural provisions, including those related to limitation, should be applied retrospectively unless they adversely affect vested rights.

5. Repealing and Saving Clause of FEMA:
The Court examined Section 49 of FEMA, which is the repealing and saving clause, and Section 6 of the General Clauses Act, 1897. Section 49 of FEMA does not withdraw or take away the vested right of appeal for causes of action arising under FERA. The procedural provisions of FEMA, including the proviso to sub-section (2) of Section 19, apply to appeals filed under FEMA, even if the cause of action arose under FERA. The Court concluded that the Tribunal and the High Court erred in assuming that the limitation period was governed by Section 52(2) of FERA.

Conclusion:
The Supreme Court held that the Appellate Tribunal under FEMA could entertain the appeal after the prescribed period of 45 days if it is satisfied that there was sufficient cause for not filing the appeal within the said period. The orders passed by the Tribunal and the High Court were set aside, and the matter was remitted back to the Tribunal for fresh consideration in accordance with the findings recorded by the Court. The appeals were disposed of accordingly.

 

 

 

 