Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + HC Companies Law - 2013 (4) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2013 (4) TMI 507 - HC - Companies Law


Issues Involved:
1. Validity of the award under Section 34 of the Arbitration and Conciliation Act, 1996.
2. Delay in completion of work and attribution of responsibility.
3. Legality of levying compensation under clause 2 of the agreement.
4. Claims for compensation and damages.
5. Award of interest and costs by the Arbitrator.

Detailed Analysis:

1. Validity of the Award under Section 34 of the Arbitration and Conciliation Act, 1996:
The petitioner challenged the award dated 20th November 2009, under Section 34 of the Arbitration and Conciliation Act, 1996. The court upheld the award, finding no grounds for interference as it was passed after considering the facts and evidence presented by both parties.

2. Delay in Completion of Work and Attribution of Responsibility:
The respondent was awarded the work of constructing a link road underpass with a completion deadline of 23rd May 1996. However, due to breaches by the petitioner, the work was completed on 28th March 2000, resulting in a delay of 1435 days. The Arbitrator found that 1309 days of delay were attributable to the petitioner, and the remaining 126 days were unjustly penalized.

3. Legality of Levying Compensation under Clause 2 of the Agreement:
The Arbitrator concluded that the compensation levied by the Superintending Engineer for 126 days was unjustified. The Arbitrator cited multiple judgments to support the decision that the levy of compensation under clause 2 was inequitable and redundant since the time was not the essence of the contract. The Arbitrator emphasized that the entitlement to compensation should be decided by the Arbitrator, while the quantum could be determined by the Superintending Engineer.

4. Claims for Compensation and Damages:
- Claim No.1: Partially allowed, awarding Rs.1,80,516/- for the undisputed quantity of I-Section.
- Claim No.6: Partially allowed, awarding Rs.57,847/- for the steel struts embedded in the raft portion.
- Claim No.7: The Arbitrator found the levy of compensation under clause 2 to be invalid.
- Claim No.8: Allowed, awarding Rs.5,00,000/- under clause 10(cc) for work executed during the last four months.
- Claim No.10: Allowed, awarding Rs.5,07,500/- for damages.
- Claim No.16: Allowed, awarding Rs.50,000/- for the cost of arbitration proceedings.

5. Award of Interest and Costs by the Arbitrator:
The Arbitrator awarded interest at 12% per annum from 3rd May 2002 until the date of the award and until realization. The court found this rate to be reasonable, considering that nationalized banks charge more than 12% on clean loans for commercial activities. The award of Rs.50,000/- as the cost of arbitration proceedings was also upheld.

Conclusion:
The court dismissed the objections filed by the petitioner, finding no merit in them. The award passed by the Arbitrator was upheld, and the petitioner was held responsible for the delays. The compensation levied under clause 2 was deemed invalid, and the claims for damages and costs were justified. The interest rate awarded by the Arbitrator was considered appropriate. No costs were imposed on the petitioner for the objections filed.

 

 

 

 

Quick Updates:Latest Updates