Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2016 (12) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2016 (12) TMI 1763 - SC - Indian Laws


Issues Involved:
1. Validity of the Certificate issued by the Independent Engineer (IE).
2. Whether the Commercial Operation Date (COD) of Unit No. 3 was achieved on 31.3.2013.
3. Whether the procurers waived the requirement of achieving 95% of the contracted capacity for COD.
4. Impact of waiver on public interest and consumer tariffs.
5. The role and findings of the Central Electricity Regulatory Commission (CERC) and the Appellate Tribunal.

Detailed Analysis:

1. Validity of the Certificate issued by the Independent Engineer (IE):
The Independent Engineer (IE) issued a certificate on 30.3.2013 stating that the performance test for Unit No. 3 was carried out in accordance with Schedule 5 of the Power Purchase Agreement (PPA) and that the unit achieved a tested capacity of 101.38 MW. However, the Supreme Court found that the certificate was not in compliance with Article 6.3.1 and Schedule 5 of the PPA, which required the unit to operate continuously for 72 hours at 95% of its contracted capacity (587 MW). The Court agreed with the Central Electricity Regulatory Commission (CERC) that the certificate was flawed and not a final test certificate as required by the PPA.

2. Whether the Commercial Operation Date (COD) of Unit No. 3 was achieved on 31.3.2013:
The bone of contention was whether COD was achieved on 31.3.2013. The Supreme Court held that COD could not be declared on 31.3.2013 as the performance test did not meet the 95% contracted capacity requirement. The Court noted that the performance tests conducted between 1st April and 16th August 2013 showed that the unit did not achieve the required capacity until June 2013. Therefore, the COD could only be declared on 16.8.2013, when the final test certificate was issued.

3. Whether the procurers waived the requirement of achieving 95% of the contracted capacity for COD:
The Supreme Court examined the emails and correspondence between the parties to determine if there was a waiver. The Court found that the lead procurer's email on 31.3.2013 categorically stated that the test result was not acceptable as it did not meet the 95% requirement. A subsequent email on 2.4.2013 accepted the performance test under Article 6.3.4 of the PPA for a de-rated capacity of 101.38 MW, but this was without prejudice to their rights. The Court concluded that there was no clear and unequivocal intention to waive the 95% requirement, and thus, no waiver occurred.

4. Impact of waiver on public interest and consumer tariffs:
The Supreme Court emphasized that any waiver affecting the tariff payable by consumers would impact public interest. The Court referred to Sections 61 to 63 of the Electricity Act, 2003, which mandate safeguarding consumer interests and ensuring reasonable recovery of electricity costs. The Court held that any waiver of the requirement under Article 6.3.1 and Schedule 5 would affect consumer tariffs and public interest, and therefore, such a waiver cannot be allowed.

5. The role and findings of the Central Electricity Regulatory Commission (CERC) and the Appellate Tribunal:
The CERC, in its order dated 8.8.2014, found that the COD was not achieved on 31.3.2013 and set the date as 16.8.2013. The Appellate Tribunal, however, held that the procurers had waived the 95% requirement and accepted the COD as 31.3.2013. The Supreme Court set aside the Appellate Tribunal's judgment, reinstating the CERC's findings. The Court noted that the Appellate Tribunal's conclusion on waiver was erroneous and that the Independent Engineer's certificate did not comply with the PPA requirements.

Conclusion:
The Supreme Court allowed the appeals, setting aside the Appellate Tribunal's judgment and reinstating the CERC's order. The Court held that the COD could only be declared on 16.8.2013, as the performance test on 31.3.2013 did not meet the 95% contracted capacity requirement. The Court also found no waiver of the requirement by the procurers and emphasized the impact on public interest and consumer tariffs.

 

 

 

 

Quick Updates:Latest Updates