Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2020 (12) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (12) TMI 1372 - SC - Indian Laws


Issues Involved:
1. Breach of contract by not lifting the contracted quantity of coal.
2. Appellant's ability to supply coal during the Fifth Delivery Period.
3. Limitation period for the claim.
4. Proof and calculation of damages.

Detailed Analysis:

1. Breach of Contract by Not Lifting the Contracted Quantity of Coal:
The Majority Award found that the Respondent failed to lift 454,034 metric tonnes of coal during the Fifth Delivery Period, constituting a breach of contract. The Respondent's contention that the Appellant did not have the goods available for delivery was rejected. The Tribunal noted that the Respondent sought further deliveries of coal at a price lower than the contract price, which the Appellant refused. The Majority Award concluded that the Respondent's failure to lift the contracted quantities was due to its unwillingness to pay the contractual price, not the Appellant's inability to supply.

2. Appellant's Ability to Supply Coal During the Fifth Delivery Period:
The Majority Award accepted the evidence of Mr. John B. Wilcox, the Appellant's Marketing Manager, who testified that the Appellant had sufficient coal to meet the contract requirements. The Tribunal found that the Appellant was producing around 1,000,000 tonnes per month during the relevant period and had made distress sales at prices far below the contract price due to a slump in the market. The Majority Award rejected the Respondent's claim that the Appellant was unable to supply coal, noting that the Respondent's own letters indicated a request for price reduction due to market conditions.

3. Limitation Period for the Claim:
The Tribunal held that the claim was not barred by limitation. The notice of arbitration was issued on 24th September 2012, within the three-year limitation period from the date of the breach, which was determined to be 30th September 2009.

4. Proof and Calculation of Damages:
The Majority Award found that the Appellant had proven the market price of coal at the time of breach through Mr. Wilcox's affidavits and contemporaneous correspondence. The difference between the contract price ($300 per metric tonne) and the market price ($128 per metric tonne) was used to calculate damages. The Tribunal awarded the Appellant $78,720,414.92 in damages, with interest and costs.

Separate Judgments:
The Dissenting Award by Justice V.K. Gupta found that the Appellant did not have the contracted material ready to supply and had diverted the material to third parties. It concluded that the Appellant was in breach and not entitled to damages. However, this view was not upheld by the Majority Award or the subsequent judicial reviews.

Judicial Review:
The Single Judge upheld the Majority Award, rejecting the Respondent's plea of limitation and finding no grounds for interference under Section 34 of the Arbitration and Conciliation Act, 1996. The Division Bench, however, set aside the Majority Award, finding that the inferences drawn by the Tribunal were based on "imaginary evidence" and not supported by the correspondence between the parties. The Supreme Court, however, restored the Majority Award, finding that the Division Bench's approach was flawed and that the Majority Award was a possible view based on the evidence presented.

 

 

 

 

Quick Updates:Latest Updates