Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2018 (1) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2018 (1) TMI 921 - SC - Indian Laws


Issues Involved:
1. Validity of the Arbitral Award.
2. Breach of Contract by the Appellant.
3. Waiver of Rights by the Respondent.
4. Calculation and Award of Damages.
5. Mitigation of Damages.
6. Scope of Judicial Interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
7. Public Policy Considerations.

Detailed Analysis:

1. Validity of the Arbitral Award:
The appellant challenged the Arbitral Award dated June 18, 2004, which directed it to pay ?185,97,86,399/- to the respondent as damages. The appellant's application under Section 34 of the Arbitration and Conciliation Act, 1996, questioning the correctness of the Award, was dismissed by the learned Single Judge of the High Court, and the intra-court appeal was also dismissed by the Division Bench of the High Court. The Supreme Court upheld the High Court's decision, affirming the validity of the Arbitral Award.

2. Breach of Contract by the Appellant:
The respondent contended that the appellant breached the contract by not supplying the list of locations where the contract objects had to be installed and not renewing the Letter of Credit (LC). The Arbitral Tribunal found that the appellant had committed a fundamental breach by failing to supply the DTC lists, which was a fundamental term of the contract. This finding was upheld by both the Single Judge and the Division Bench of the High Court. The Supreme Court agreed with this assessment, stating that the appellant's failure to provide the DTC lists prevented the respondent from performing its contractual obligations.

3. Waiver of Rights by the Respondent:
The appellant argued that the respondent had waived its right to receive the complete list of locations. However, the Arbitral Tribunal and the High Court found no merit in this argument. The Tribunal noted that the respondent had acted reasonably and did not insist on strict compliance with every term of the contract, which did not constitute a waiver of its rights. The Supreme Court upheld this view, stating that the respondent's actions did not amount to a waiver of its right to receive the DTC lists.

4. Calculation and Award of Damages:
The Arbitral Tribunal awarded damages based on the loss suffered by the respondent due to the appellant's breach. The Tribunal calculated damages for installed objects, stranded objects, and objects not manufactured. The High Court found that the Tribunal had adopted a reasonable method for calculating damages, which was in line with the principle that the injured party should be placed in as good a position as if the contract had been performed. The Supreme Court upheld this approach, stating that the Tribunal's method of calculating damages was reasonable and plausible.

5. Mitigation of Damages:
The appellant argued that the respondent had not taken steps to mitigate its losses. However, the Arbitral Tribunal found that the contract objects were custom-built and could not be disposed of in the open market. The Tribunal noted that the respondent had made efforts to sell the stranded objects to other electricity boards, but these efforts were unsuccessful. The High Court and the Supreme Court agreed with this finding, stating that the respondent had made reasonable efforts to mitigate its losses.

6. Scope of Judicial Interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996:
The High Court discussed the scope of interference under Sections 34 and 37 of the Act, particularly in relation to the ground of public policy. The Court noted that findings of fact by the Arbitral Tribunal, based on the evidence on record, should not be scrutinized as if the Court was sitting in appeal. The Supreme Court upheld this view, stating that the Arbitral Tribunal is the master of evidence, and its findings should not be interfered with unless there is a clear case of perversity.

7. Public Policy Considerations:
The appellant argued that the Award was against public policy. However, the High Court and the Supreme Court found no merit in this argument. The Supreme Court noted that the Award was based on a detailed examination of the facts and evidence and that the Tribunal had adopted a reasonable method for calculating damages. The Court concluded that the Award was not contrary to public policy.

Conclusion:
The Supreme Court upheld the Arbitral Award and dismissed the appellant's appeal with costs. The Court found that the appellant had committed a fundamental breach of the contract by failing to provide the DTC lists, and the respondent was entitled to damages for the loss suffered. The Court also held that the respondent had not waived its rights and had made reasonable efforts to mitigate its losses. The findings of the Arbitral Tribunal were based on a thorough examination of the evidence and were not to be interfered with by the Court.

 

 

 

 

Quick Updates:Latest Updates