Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + Other Indian Laws - 2021 (3) TMI Other This

  • Login
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (3) TMI 976 - Other - Indian Laws


Issues Involved:
1. Delay in project completion and lack of common facilities.
2. Non-registration of the project with RERA.
3. Discrepancies in the status of the project.
4. Defects in the occupied flats.
5. Transfer of common facilities to the service provider.
6. Maintenance and repair responsibilities.
7. Jurisdiction and maintainability of the complaint.
8. Compliance with RERA provisions.
9. Ownership and transfer of common amenities.
10. Refund of security deposits.

Detailed Analysis:

1. Delay in Project Completion and Lack of Common Facilities:
The complainant association highlighted that the project 'Serene Rose' was promised for completion by June 2016 but was delayed significantly. Common facilities like electricity, boundary wall, staff quarters, medical center, and internal roads were incomplete even when some occupants moved in by October 2017. The service lift was commissioned only in March 2019, and the completion certificate was still pending.

2. Non-Registration of the Project with RERA:
The complainants pointed out that the 1st Respondent did not register the 'Serene Rose' project with RERA, violating RERA rules. The 1st Respondent argued that phases A and C were launched before RERA's introduction and thus did not fall under its ambit. However, phases B and D were registered with RERA.

3. Discrepancies in the Status of the Project:
The complainants noted contradictions in the status of the project as reported by the 1st Respondent in different documents. While the project was claimed to be "nearing completion" and "completed and handed over," many facilities were still incomplete.

4. Defects in the Occupied Flats:
The complainants listed several defects in the occupied flats, including leakages, blocked pipelines, and unfinished works. The 1st Respondent acknowledged the responsibility to attend to these defects within twelve months from the date of possession, as per the construction agreement.

5. Transfer of Common Facilities to the Service Provider:
The complainants argued that common facilities were sold to the service provider, which should have been handed over to the Residents Welfare Association as per RERA rules. The 1st Respondent contended that the amenities were transferred to the service provider for maintenance purposes.

6. Maintenance and Repair Responsibilities:
The 1st Respondent claimed that all repair and maintenance works reported within twelve months of possession were attended to. The complainants, however, stated that many defects remained unresolved despite being reported within the stipulated period.

7. Jurisdiction and Maintainability of the Complaint:
The 2nd Respondent (service provider) argued that the complaint was not maintainable before RERA as there was no provision mandating the registration of a "service provider" under RERA. They also contended that the association had no locus standi to file the complaint.

8. Compliance with RERA Provisions:
The complainants argued that the entire project should be considered a single integrated project under RERA's ambit. The authority determined that the project, including common amenities, was not completed by the crucial date of 01.05.2017, thus classifying it as an ongoing project under RERA.

9. Ownership and Transfer of Common Amenities:
The authority directed the 1st Respondent to register Block-A and C along with common areas and amenities with RERA. The 1st Respondent was also instructed to execute a registered conveyance deed for the title in common areas and amenities to the Association of Allottees by 28.02.2021. The sale of undivided share of land to the service provider was found to be in contravention of RERA provisions and the construction agreement.

10. Refund of Security Deposits:
The complainants sought the refund of security deposits collected from the owners. The 2nd Respondent argued that the refundable deposit was a caution measure and did not fall under RERA's purview. The authority did not directly address the refund issue but focused on compliance with RERA provisions.

Conclusion:
The authority concluded that the project was an ongoing project under RERA and directed the 1st Respondent to register the project and hand over common amenities to the association. The sale of land and club house to the service provider was declared null and void, and the 1st Respondent was instructed to rectify defects reported within five years of possession. The service agreement with the service provider was deemed null and void to the extent it conflicted with RERA provisions.

 

 

 

 

Quick Updates:Latest Updates