Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2024 (4) TMI SC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2024 (4) TMI 425 - SC - Indian Laws


Issues Involved:
1. Interpretation of contract conditions for measurement and payment of embankment construction.
2. Validity of the arbitral award and the scope of judicial interference under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996.

Summary:

Issue 1: Interpretation of Contract Conditions
The core issue was the interpretation of a contract condition regarding the measurement of quantities for payment in embankment construction using soil or pond ash. The contractors argued for a composite measurement of the entire cross-section using the average end area method, while the supervising engineer (EE) measured soil and pond ash separately. The contractors claimed this was against Technical Specification (TS) Clause 305.8. The National Highways Authority of India (NHAI) supported the EE's method.

Issue 2: Validity of the Arbitral Award and Scope of Judicial Interference
The arbitral tribunal, comprising three technical experts, issued an award favoring the contractors' interpretation, with a dissenting opinion from one arbitrator. The contractors challenged both the unanimous and majority views under Section 34 of the Arbitration and Conciliation Act, 1996. The Single Judge upheld the majority view, stating it was a plausible interpretation that did not warrant interference. The Division Bench, however, set aside this decision, deeming the majority view implausible.

Contentions of Parties:
- Contractors: Argued that the Division Bench exceeded its jurisdiction under Sections 34 and 37 of the Act, which restricts grounds for challenging an arbitral award. They emphasized the technical nature of the contract conditions and the need for deference to the tribunal's findings. They highlighted that the contract contemplated two types of embankments and that the method of measurement should be composite.
- NHAI: Argued that the tribunal's interpretation was incorrect and led to absurd results. They contended that separate measurements were necessary due to varying ratios of soil and pond ash. They highlighted that for two years, separate measurements were taken, and embankment construction involved layering, making separate measurements feasible.

Analysis and Conclusions:
The Supreme Court emphasized the limited scope of judicial review under Section 34, which does not allow for appellate review of arbitral awards. The Court noted that the tribunal's majority view was plausible and should not have been substituted by the Division Bench. The Court reiterated the principle that arbitral awards, especially those involving technical expertise, should not be lightly interfered with unless they are perverse or based on a wrong proposition of law.

Final Decision:
The Supreme Court allowed the appeals, set aside the judgments of the Delhi High Court, and upheld the arbitral awards. The Court modified the interest payments, directing NHAI to pay uniform interest at 12% from the date of the award to the date of payment within eight weeks. There were no directions to pay costs.

 

 

 

 

Quick Updates:Latest Updates