Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2014 (10) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2014 (10) TMI 589 - SC - Indian Laws


Issues Involved:
1. Material term of the contract regarding the national origin of hydrophones.
2. Justification of refusal to allow substitution of Canadian hydrophones.
3. Validity of force majeure declaration.
4. Delay in performance of the contract.
5. Responsibility for the delay.
6. Entitlement to damages.
7. Entitlement to adjust sums payable.
8. Entitlement to both Liquidated Damages and Excess Engagement charges.

Issue-wise Detailed Analysis:

1. Material Term of the Contract Regarding National Origin of Hydrophones:
The Arbitral Tribunal held that the national origin of hydrophones was not a material term of the contract. The choice of hydrophones was left to the bidders as long as the equipment met the prescribed specifications, and there was no stipulation regarding the make or country of origin.

2. Justification of Refusal to Allow Substitution of Canadian Hydrophones:
The Tribunal found that once the respondent contracted to supply U.S. made hydrophones, the appellant-Corporation was entitled to insist on the contracted equipment. The Tribunal concluded that the appellant was not justified in insisting on pursuing the U.S. license further once the respondent informed them that the option was closed.

3. Validity of Force Majeure Declaration:
The Tribunal decided against the respondent, stating that none of the events mentioned in the contract had taken place to justify invoking the force majeure clause. Since the parties did not belong to the U.S., the force majeure clause could not be validly invoked.

4. Delay in Performance of the Contract:
The Tribunal acknowledged that there was a delay in delivering the vessel back to the appellant. The vessel should have been returned by 9th July 2001 but was instead returned on 6th May 2002. The Tribunal found that the delay from 10th July 2001 to 31st March 2001 was attributable to the respondent.

5. Responsibility for the Delay:
The Tribunal attributed the delay between 1st November 2001 and 22nd March 2002 to the appellant-Corporation. The delay in taking decisions and conveying information was primarily the appellant's responsibility.

6. Entitlement to Damages:
The Tribunal held that the appellant-Corporation was entitled to liquidated damages and excess engagement charges under the contract. However, the deductions for the period from 1st November 2001 to 22nd March 2002 were not justified and were to be released to the respondent.

7. Entitlement to Adjust Sums Payable:
The Tribunal ruled that deductions made by the appellant towards taxes were not permissible. Since the work was executed in Singapore, no Indian taxes were applicable, and the deductions were unjustified.

8. Entitlement to Both Liquidated Damages and Excess Engagement Charges:
The Tribunal decided that the appellant-Corporation was justified in making deductions for liquidated damages and excess engagement charges except for the period from 1st November 2001 to 22nd March 2002.

High Court and Supreme Court Judgments:
The High Court upheld the Tribunal's findings except for the award of pendente lite and future interest, which was waived by the respondent. The Supreme Court modified the award by reducing the period attributable to the appellant-Corporation by 56 days, thus affirming deductions for that period and reducing the amount payable to the respondent proportionately.

Conclusion:
The Supreme Court's final judgment allowed the appeal to the extent of modifying the period of delay attributable to the appellant-Corporation, resulting in a proportionate reduction in the amount payable to the respondent. The deductions for taxes were deemed unjustified, and the award was modified accordingly.

 

 

 

 

Quick Updates:Latest Updates