Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2021 (9) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (9) TMI 1154 - SC - Indian Laws


Issues Involved:
1. Determination of the date from which the 42 months period for handing over possession is to be calculated.
2. Whether the terms of the Apartment Buyer’s Agreement were one-sided.
3. Whether the provisions of the Real Estate (Regulation and Development) Act, 2016 must be given primacy over the Consumer Protection Act, 1986.
4. Whether on account of the inordinate delay in handing over possession, the Apartment Buyers were entitled to terminate the agreement and claim a refund of the amounts deposited with interest.

Detailed Analysis:

1. Determination of the date from which the 42 months period for handing over possession is to be calculated:
The court examined whether the 42 months period should be calculated from the date of issuance of the Fire NOC or from the date of sanction of the Building Plans. The court held that it was mandatory under the Haryana Fire Safety Act, 2009 to obtain the Fire NOC before commencing construction. The 42 months period in Clause 13.3 of the Agreement for handing over possession of the apartments would be required to be computed from the date on which Fire NOC was issued, not from the date of the Building Plans being sanctioned. The Fire NOC was obtained on 27.11.2014, thus the Commitment Period of 42 months plus the Grace Period of 6 months would end on 27.11.2018.

2. Whether the terms of the Apartment Buyer’s Agreement were one-sided:
The court found that the terms of the Agreement were wholly one-sided and loaded in favor of the Developer. Clauses such as Clause 7.4 requiring buyers to pay interest at 20% per annum on delayed payments, Clause 13.2 imposing “Holding Charges” on buyers who delayed taking possession, and Clause 13.5 limiting compensation for delay to 12 months only, were highlighted as particularly unfair. The court held that these terms constituted an unfair trade practice under Section 2(1)(r) of the Consumer Protection Act, 1986, and were not binding on the apartment buyers.

3. Whether the provisions of the Real Estate (Regulation and Development) Act, 2016 must be given primacy over the Consumer Protection Act, 1986:
The court held that the remedies under the Consumer Protection Act, 1986 are in addition to, and not in derogation of, any other law applicable, including the RERA Act. The court emphasized that Section 88 of the RERA Act states that its provisions are in addition to and not in derogation of other laws. The court also noted that the Consumer Protection Act provides a remedy for better protection of the interests of consumers, including the right to seek redressal against unfair trade practices. Therefore, the Consumer Protection Act and the RERA Act could coexist, and consumers could choose their remedy.

4. Whether on account of the inordinate delay in handing over possession, the Apartment Buyers were entitled to terminate the agreement and claim a refund of the amounts deposited with interest:
The court categorized the allottees into two groups: those in Phase 1, where possession was offered after the issuance of the Occupation Certificate, and those in Phase 2, where the Occupation Certificate had not been issued. For Phase 1 allottees, the court held that they were obligated to take possession but were entitled to Delay Compensation for the period of delay. For Phase 2 allottees, the court held that they were entitled to a refund of the entire amount deposited due to the inordinate delay and the absence of an Occupation Certificate. The court directed the Developer to refund the amounts with interest at 9% per annum from 27.11.2018 till the date of payment, and in some cases, within a specified period, failing which a higher rate of interest would apply.

Conclusion:
The court concluded that the Developer could not compel the apartment buyers to be bound by the one-sided contractual terms and that the remedies under the Consumer Protection Act were available in addition to the RERA Act. The court provided specific directions for refunds and compensation based on the categorization of the allottees.

 

 

 

 

Quick Updates:Latest Updates