Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

TMI Blog

Home

2001 (1) TMI 921

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... consistency between the particulars given in the annexure and the total bid amount, it cannot be directed to be considered along with other bid on the sole ground of being the lowest. We find no force in the submission that as under Clause 14.2 items against which no rate or price is entered by the bidder will not be paid by the employer when executed and shall be deemed covered by the other rates and prices in the bill of quantities, the unit price in items containing errors be ignored and the bid be considered on the basis of total price bid which is the lowest. In our view, there is a basic distinction between a case where against some items no rates or prices are quoted and a case where some rate is quoted. Whereas in the former case the bidder will not be entitled to claim any specific amount for the work done by him in the absence of any rate for that work, because in the aforementioned clause it is clarified that the bidders will not be paid by the employer and that the execution of the work shall be deemed covered by other rates and prices in the bill of quantities but in the latter case the bidder will be entitled to claim for the work executed on the basis of quoted price .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... which Lot No.4 relates to main civil works. For carrying out the work of Lot No.4, the appellant, after complying with the formalities and after satisfying itself of the pre- qualification of the bidders, invited revised tenders (hereinafter referred to as, the tenders). The bids were to be submitted on or before April 27, 1998. Three bidders are now in fray. The first is a consortium of four companies (respondent Nos.1 to 4), the second is M/s. Taisei Corporation (respondent No.10) and the third is M/s. Skanska International (respondent No.11). They submitted their bids along with the summary sheets thereof. On September 8, 1999 the bids were opened in the presence of the representatives of the bidders and they were read out; the bid of respondent Nos.1 to 4 was Rs.647.90 crores, of respondent No.11 was Rs.691.22 crores and of respondent No.10 was 726.50 crores. While the details of the bid were under scrutiny, by letter dated October 25, 1999, respondent Nos.1 to 4 informed the appellant that there was a repetitive systematic computer typographical transmission failure and requested that it be corrected. On December 17, 1999 they sent another letter stating that they had reason .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... ected the appellant to permit respondent Nos.1 to 4 to correct the errors in the bid documents and then consider their bid along with the other bids and take a decision objectively and rationally. Mr. Altaf Ahmed, the learned Additional Solicitor General, appearing for the appellant, has submitted that the appellant is bound by the ITB and it acted accordingly. The letter dated October 25, 1999 of respondent Nos.1 to 4 did not indicate the errors in the bid documents and the correction sought by them. Even their letter of December 17, 1999 did not specify in any detail the desired corrections, therefore, the appellant proceeded to evaluate the bid in terms of ITB. The actual scope of correction sought by respondent Nos.1 to 4 came to light in their representation dated December 23, 1999, filed after approaching the High Court. The appellant, submitted the learned Additional Solicitor General, committed no wrong in rejecting the representation as the same was not acceptable in terms of Clause 29 of the ITB because neither the unit rate can be changed nor the price bid can be altered at the request of the bidder; the unit rate quoted is final and the appellant can correct only arithm .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... n the basis of an unintended unit rate to reach an astonishing figure which was wholly disproportionate to the cost of the Project. His contention is that once the total bid price is maintained, the unit rate is a matter of arithmetic exercise which should have been corrected by the appellant; further the mode of payment by the appellant for the work done is not on the basis of each unit but on the basis of bid price. Accepting that the bid price is unalterable, the unit rate should be regarded as adjustable. It was also argued by Mr. Chidambaram that there was no mistake in giving the unit rate as such; the mistake was in giving the conversion equivalent in US Dollars and, therefore, the correction not being the one falling under Clause 29 of the ITB was rightly permitted to be corrected by the High Court. Finally, he contended that their bid being less than the bids of respondent Nos.11 and 10 by Rs.40 crores and Rs.80 crores respectively, the High Court rightly directed consideration of the bid of respondent Nos.1 to 4 after due correction of the bid documents in public interest which did not warrant interference by this Court. In the light of the above contentions, we have to e .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... ht, offered or permitted except as required to confirm the correction of arithmetic errors discovered by the Employers authorised representative in the evaluation of the bids in accordance with Clause 29 of ITB. 29. Correction of Errors 29.1 Bids determined to be substantially responsive will be checked by the Employers authorised representative for any arithmetic errors. Errors will be corrected by the Employers authorised representative as follows: (a) where there is a discrepancy between the amounts in figures and in words, the amount in words will govern; and (b) where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by the quantity, the unit rate as quoted will govern. (c) Where there is a discrepancy between figures and in words of an unit rate, the unit rate as quoted in words will govern. 29.2 The amount stated in the Form of Bid will be adjusted by the Employers authorised representative in accordance with the above procedure for the correction of errors and shall be communicated to the Bidder in writing for his acceptance in writing within seven (7) days from the date of issue of such communication. Such cor .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... and the bid security is liable to be forfeited in accordance with sub- clause 17.6 (b) of the ITB. Now adverting to the Annexures, the statement of B.Upper Dam price bid submitted by respondents 1 to 4 discloses that with reference to each work item the quantity thereof is mentioned. The bidder is expected to give the unit price in Indian Rupee as well as in U.S. Dollar both in figures as well as in words and enter the line item total resulting from multiplying the unit rate by the quantity. A plain reading of sub-clause (b) of Clause 29.1, referred to above, leaves no room for doubt that once the unit rate and line item total are filled in by the bidder, both the quoted unit rate and item total are treated as unalterable at the instance of the bidder though arithmetic errors in arriving at line item total by multiplication are permitted to be corrected by the appellants authorised representative. This being the intendment of the ITB, we shall now examine : (i) whether the correction made by the appellant in the bid documents of respondent Nos.1 to 4 and consequential evaluation of their bid communicated with letter dated December 18, 1999 are valid in law; and (ii) whether resp .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... items in the bid documents. We shall extract here, as a sample of errors in 37 items, the price bid submitted by respondent Nos.1 to 4 relating to B. Upper Dam found on page No.70 of Vol.IV of the documents (marked A). It reads thus: Annexure B. Upper Dam A Price Bid as Submitted Item Work Item Esc. Coeff. Remarks Unit Quantity Unit Price Amount Clause In Specifica- tions INR US$ Figure Words 1.Care of river 02 Rock Excavation 3,384.64 Cum 1000 148.08 148.08 148,077.97 7.4 One hundred forty-eight point nil eight One hundred forty-eight point nil eight 03 Impervious Core Embankment 7,506.71 Cum 148.08 1.92 328,418.53 9.5 One hundred forty-eight point nil eight One point ninety-two According to respondents 1 to 4, the above price bid should be corrected to read as given in the following statement (marked B): Work Item Esc. Coeff. Remarks Unit Quantity Unit Price Amount Clause In Specifica- tions INR US$ Figure Words 1.Care of river 02 Rock Excavation 3,384.64 Cum 1000 148.08 148.08 148,077.97 7.4 One hundred forty-eight point nil eight One hundred forty-eight point nil eight 03 Impervious Core Embankment 7,506.71 3,900 84..21 1 .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... no discrepancy as envisaged in sub-clause (b) of Clause 29.1. It would not really be a case of incorporating a new unit rate but a case of either recording U.S. Dollar equivalent of the unit rate already noted in Indian Rupee or vice versa as given in statement B above. In such a case, perhaps, they would have been entitled to equitable relief of rectification of mistake. But here, as would be shown presently, the position is different. With regards to the mistakes in the bid documents, for the first time respondent Nos.1 to 4 informed the appellant in their letter of October 25, 1999 which runs as follows : Re : Purulia Pumped Storage Project Lot 4 - Main Civil Works - Resubmittal Price Bid. Dear Sirs, We regret that certain repetitive systematic computer typographical data transmission failure have occurred in items as per attached annexure in our bid submitted to you on 08.09.99. In order to dispel any doubts, we hereby unconditionally declare that we stand by the amounts (both INRs and US $) against the affected schedules A to I, announced at the opening of the revised price bid on the 8th of September at WBSEB and reiterate that there is no change in the price or substance o .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... we have all along maintained and still maintain the said bid price of Rs.647.90 crores. However, we have reasons to believe that you have chosen to ignore our said letter and have proceeded to evaluate our price bid by an illogical and mis-application of the rules for the evaluation of the bids set down in the ITB. We, therefore, once again call upon you to evaluate our bid after taking into consideration the applicable unit rates. As already mentioned in our earlier fax there is no change in the price or substance of our bid as mentioned in the amount column of the BOQ. (Emphasis supplied) Here, though the nature of mistakes are pointed out yet the scope of the correction sought is not indicated. The appellant could not have ignored these letters. Had the appellant taken note of these letters and the mistakes occurring due to repetition of entries in 37 items in the bid documents, it would not have proceeded with correction of such mistakes and evaluation of their bid without first seeking clarification from respondents 1 to 4 under Clause27.1. We have already referred to the gist of that clause. The only prohibition contained therein is that no change in the price or substanc .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... our view, is right in his submission that till the representation was made by the said respondents on December 23, 1999, after the interim direction of the High Court, the appellant was unaware of the quoted unit rate being in such proportion. A combined reading of ITB and the annexure, extracted above, makes it clear that the second line against each work item is meant for writing U.S. Dollar or Japanese Yen equivalent of the unit rate and line total in the amount column entered in the first line and not for writing bifurcated unit price in different currencies in the ratio of 50 : 50. On these facts, the errors cannot be termed as mere clerical or mechanical. Permitting correction of such errors, if they can be so called, would result in not only re-writing unit rates in 37 entries in which such errors are said to have been committed but also appending an explanation thereto regarding splitting of unit rates in terms of representation dated 23.12.1999 of respondent Nos.1 to 4. Neither Clauses 27 and 29 nor any other clause in the ITB permits such corrections. The mistakes/errors in question, it is stated, are unintentional and occurred due to the fault of computer termed as a re .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... t adherence to ITB or Rules is the best principle to be followed, which is also in the best public interest. For all these reason, in such a highly competitive bid of global tender, the appellant was justified in not permitting respondent Nos. 1 to 4 to correct the errors of the nature and the magnitude which, if permitted, will give a different complexion to the bid. The High Court erred in directing the appellant to permit respondent Nos.1 to 4 to correct the errors in the bid documents. Mr. Chidambram, however, submitted that in equity respondent Nos.1 to 4 would be entitled to relief of correction of mistakes. He invited our attention to para 84 of the American Jurisprudence (Second Edition, Volume 64, Page No.944). It will be useful to quote the relevant part of that para here: As a general rule, equitable relief will be granted to a bidder for a public contract where he has made a material mistake of fact in the bid which he submitted, and where, upon the discovery of that mistake, he acts promptly in informing the public authorities and requesting withdrawal of his bid or opportunity to rectify his mistake particularly where he does so before any formal contract is entered i .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... s might be claimed to be pertinent to that case even though the transactions between the parties be considered as a completed contract and held that the action of the City of Rochester in awarding one contract to another bidder and forcing the plaintiff to enter into the second contract after it had declared there was a mistake in its proposal was inequitable. Exceptions to the above general principle of seeking relief in equity on the ground of mistake, as can be culled out from the same para, are : (1) where the mistake might have been avoided by the exercise of ordinary care and diligence on the part of the bidder; but where the offeree of the bid has or is deemed to have knowledge of the mistake, he cannot be permitted to take advantage of such a mistake. (2) where the bidder on discovery of the mistake fails to act promptly in informing to the concerned authority and request for rectification, withdrawal or cancellation of bid on the ground of clerical mistake is not made before opening of all the bids, (3) where the bidder fails to follow the rules and regulations set forth in the advertisement for bids as to the time when bidders may withdraw their offer; however where the m .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... ard Spinas bid was calculated which obviously worked out far higher than the intended bid amount. Taking note of that amount the Borough awarded the contract to Tomaro. Spina instituted action claiming that the Borough arbitrarily failed to recognise that its bid was lower than that of Tomaro. The Law Division held that the error in the bid was non-material and subject to waiver. The Superior Court while agreeing with the Law Division observed that they did not hold that generally an error in the statement of a price could be treated as immaterial and it was only when as in that case the error was patent and the true intent of the bidder obvious that such an error might be disregarded. The Superior Court held that when as in that case the failure to waive the deviation would thwart the aims of the public bidding laws, the municipality was obliged to grant the waiver. (Emphasis supplied) Though Clause 29 in this case appears to be similarly worded as in the bid documents in Spinas case (supra), a close reading of these clauses shows that no power of waiver is reserved in the case on hand. That apart, the nature of the error in these two cases is entirely different. There, the error .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... uantities, the unit price in items containing errors be ignored and the bid be considered on the basis of total price bid which is the lowest. In our view, there is a basic distinction between a case where against some items no rates or prices are quoted and a case where some rate is quoted. Whereas in the former case the bidder will not be entitled to claim any specific amount for the work done by him in the absence of any rate for that work, because in the aforementioned clause it is clarified that the bidders will not be paid by the employer and that the execution of the work shall be deemed covered by other rates and prices in the bill of quantities but in the latter case the bidder will be entitled to claim for the work executed on the basis of quoted price/rate. We may, however, clarify that the appellant is not obliged to award contract to any of the bidders at their quoted price bid. It is always open to the appellant to negotiate with the next lowest bidder for awarding the contract on economically viable price bid. For the reasons abovementioned, though the impugned order of the High Court insofar as it relates to quashing of letter of the appellant dated December 18, 19 .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

 

 

 

 

Quick Updates:Latest Updates