Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + SC Companies Law - 2006 (11) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2006 (11) TMI 353 - SC - Companies Law


Issues Involved:
1. Legality of the Kerala High Court's judgment requiring the appellant to implement the order dated 19-4-1994.
2. Extension of time for completion of work and its implications.
3. Claims for compensation by HCC.
4. Formation and recommendations of the ad hoc committee.
5. Non-confirmation of minutes and its legal effect.
6. Payment of interest on delayed payments.

Issue-wise Detailed Analysis:

1. Legality of Kerala High Court's Judgment:
The Supreme Court examined the legality of the Kerala High Court's decision mandating the appellant to implement the order dated 19-4-1994. The High Court directed the issuance of consequential orders based on decisions taken on 12-4-1994 and 30-4-1994, and to make necessary payments expeditiously. The decision to cancel the earlier order on 19-4-1994, based on a meeting held on 25-1-1997 and communicated on 29-3-1997, was set aside by the High Court.

2. Extension of Time for Completion of Work:
The contract between KSEB and HCC for constructing a power tunnel was initially set to be completed by 26-10-1989. Due to delays, KSEB extended the completion time to 30-6-1992, subject to existing terms and conditions. The delays, aggregating to 47 months, were beyond HCC's control and covered under "Expected Risks" as defined in clause 8 of the contract.

3. Claims for Compensation by HCC:
HCC raised claims for compensation due to delays, which included:
- Compensation for infructuous overheads and fixed expenses: Rs. 283.80 lakhs.
- Extra incidence of equipment charges: Rs. 255.63 lakhs.
- Cost of financing: Rs. 639.25 lakhs.
- Interest on delayed payments: Rs. 56.21 lakhs.
- Extra items: Rs. 160.01 lakhs.
- Pending claims and extra items: Rs. 293.18 lakhs.
The total claim amounted to Rs. 1688.08 lakhs.

4. Formation and Recommendations of the Ad Hoc Committee:
KSEB constituted an ad hoc committee on 2-3-1993 to review HCC's claims. The committee recommended an interim release of Rs. 250 lakhs and later suggested a payment of Rs. 808.26 lakhs against HCC's aggregate claim. The committee's conclusions were based on the delays being beyond HCC's control, KSEB's continued application of contract provisions during the extended period, and HCC's right to claim compensation under clause 18 "force majeure" of the contract.

5. Non-confirmation of Minutes and its Legal Effect:
The Supreme Court emphasized that non-confirmation of minutes does not invalidate decisions taken in previous meetings. The High Court correctly noted that the decision taken on 30-4-1994 remained effective despite the minutes not being confirmed in the subsequent meeting on 30-5-1994. The Supreme Court referenced legal principles, including those from "Shackleton on the Law and Practice of Meetings" and the case "Chetkar Jha v. Viswanath Prasad Verma," to support this view.

6. Payment of Interest on Delayed Payments:
The Supreme Court ordered that Rs. 500 lakhs paid to the respondents and Rs. 300 lakhs deposited with the Court's Registry be released to the respondents with accrued interest. Additionally, the respondents were entitled to interest at a rate of 7.5% from the date of the Division Bench's judgment (15-12-1998) after adjusting amounts paid and interest elements. The balance amount was to be paid within three months.

Conclusion:
The Supreme Court dismissed the appeals with modifications, affirming the High Court's decision that the non-confirmation of minutes did not affect the earlier decision, and ordered the payment of the remaining balance with interest. No order as to costs was made.

 

 

 

 

Quick Updates:Latest Updates