Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Income Tax Income Tax + AT Income Tax - 2007 (1) TMI AT This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2007 (1) TMI 278 - AT - Income Tax


Issues Involved:
1. Determination of the actual cost for depreciation purposes.
2. Disallowance of loss arising from a construction contract.
3. Treatment of gain on cancellation of foreign exchange forward contracts.

Detailed Analysis:

Issue 1: Determination of the actual cost for depreciation purposes
The primary issue was whether the actual cost for depreciation should be based on the amount paid by the transferee company (Rs. 130.52 crore) or the written down value (WDV) in the books of the transferor company (Rs. 101.10 crore). The assessee argued that the cost should be the amount paid, while the Revenue contended it should be the WDV.

The tribunal noted that as of the transfer date, the assessee was a wholly owned subsidiary of the transferor company, invoking the provisions of section 47(iv) and Explanation 6 to section 43(1). However, the tribunal also considered the fact that the assessee ceased to be a wholly owned subsidiary within the stipulated period, thus invoking section 47A(ii), which withdraws the exemption granted under section 47(iv).

The tribunal concluded that the provisions of section 47(iv) ceased to apply, and the cost of acquisition should be the amount actually paid by the assessee. The tribunal relied on section 49(3), which states that the cost of acquisition should be the cost for which the asset was acquired by the transferee company. Thus, the tribunal directed the Assessing Officer to compute depreciation based on the actual cost of Rs. 130.52 crore.

Issue 2: Disallowance of loss arising from a construction contract
The assessee claimed a loss of Rs. 1,29,20,068 for the RAVVA project, arguing that it should be fully allowed based on the percentage completion method as per Accounting Standard No. 7. The Assessing Officer, however, allowed only 2/3rd of the estimated loss, corresponding to the percentage of the project completed during the relevant year.

The tribunal upheld the Assessing Officer's decision, noting that under the percentage completion method, the loss should be recognized proportionately to the stage of completion. Since only 2/3rd of the project was completed, only 2/3rd of the estimated loss could be claimed. The tribunal rejected the assessee's ground of appeal, affirming that future anticipated losses cannot be carried forward.

Issue 3: Treatment of gain on cancellation of foreign exchange forward contracts
The assessee received Rs. 8,62,25,383 from the cancellation of forward exchange contracts initially entered into by its parent company for purchasing fixed assets. The assessee argued that this receipt was a capital receipt and should not be deducted from the cost of the fixed assets.

The tribunal examined the facts and found that the assessee had canceled the forward contracts and received the amount as a result. The tribunal distinguished this case from the Bombay High Court decision in Bharat Forge Co. Ltd., where the compensation was for breach of contract by the bank. Instead, the tribunal found the facts similar to the Special Bench decision in Apollo Tyres Ltd., where gains from the cancellation of forward contracts related to foreign loans for purchasing machinery were to be reduced from the cost of the machinery.

The tribunal set aside the CIT(A)'s order and restored the Assessing Officer's decision to reduce the amount received from the cost of the fixed assets for depreciation purposes.

Conclusion:
The tribunal's judgment addressed the three primary issues by:
1. Allowing the assessee's appeal on the actual cost for depreciation, directing the computation based on the amount paid (Rs. 130.52 crore).
2. Upholding the disallowance of the full loss claimed for the construction contract, allowing only the proportionate loss based on the percentage completion method.
3. Reversing the CIT(A)'s decision on the treatment of gain from the cancellation of forward contracts, directing the reduction of the amount from the cost of fixed assets.

Both appeals were partly allowed, with specific directions provided for each issue.

 

 

 

 

Quick Updates:Latest Updates