Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + HC Companies Law - 2014 (2) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2014 (2) TMI 113 - HC - Companies Law


Issues Involved:
1. Reduction of building height by Airport Authority of India.
2. Notification by SEZ and its impact on the project.
3. Obligation of respondent to issue counter guarantee.
4. Allegations of fraud and suppression of documents.
5. Termination of the development agreements.
6. Discrimination against the petitioner compared to other developers.
7. Readiness and willingness of the petitioner to perform contractual obligations.

Detailed Analysis:

1. Reduction of Building Height by Airport Authority of India:
The petitioner submitted a tender based on the assumption that buildings could be constructed up to 61 meters. However, the Airport Authority of India reduced the height to 43.3 meters on 27 October 2008, later increasing it to 54.3 meters on 27 February 2010. The petitioner claimed this reduction led to financial losses and requested compensation. The respondent compensated by allocating additional land (11.644 acres) at market price. The arbitrator found that the petitioner was aware of the height restrictions and had accepted the additional land, thus rejecting the claim of delay attributed to the respondent.

2. Notification by SEZ and Its Impact on the Project:
The SEZ notification issued on 29 May 2007 imposed restrictions on the sale of flats, which the petitioner argued affected their project. The co-development agreement dated 12 May 2008 indicated that the petitioner was aware of the SEZ rules. The arbitrator concluded that the petitioner was fully aware of the SEZ restrictions and had entered into subsequent agreements with this knowledge. The arbitrator rejected the petitioner's claim that the SEZ notification was an afterthought attempt to shift responsibility.

3. Obligation of Respondent to Issue Counter Guarantee:
The petitioner argued that the respondent was obligated to issue a counter guarantee for a loan from Indiabulls, as per clause 3.7 of the agreement. The respondent had previously issued a counter guarantee for a loan from Vijaya Bank, which the petitioner defaulted on, leading to the freezing of the respondent's fixed deposits. The arbitrator found that the respondent was not obligated to issue a fresh counter guarantee under new terms proposed by Indiabulls, especially given the petitioner's default with Vijaya Bank.

4. Allegations of Fraud and Suppression of Documents:
The petitioner alleged that the respondent committed fraud by not disclosing a note from the Vice Chairman recommending the issuance of a counter guarantee to Indiabulls. The arbitrator rejected this claim, noting that the petitioner did not raise the issue of fraud in the initial pleadings and that the note was an internal document not acted upon by the respondent. The arbitrator found no merit in the fraud allegations.

5. Termination of the Development Agreements:
The respondent terminated the agreements due to the petitioner's failure to complete the project, non-payment of fees, and abandonment of work since January 2011. The petitioner argued that the agreements did not explicitly allow for termination. The arbitrator held that under the Indian Contract Act, a party could terminate a contract if the other party committed breaches. The arbitrator found the respondent justified in terminating the agreements due to the petitioner's defaults.

6. Discrimination Against the Petitioner Compared to Other Developers:
The petitioner claimed unfair treatment compared to other developers who had not completed their projects. The arbitrator rejected this claim, noting that the agreements were commercial contracts and Article 14 of the Constitution (equality before law) did not apply. The arbitrator emphasized that the agreements should be interpreted strictly according to their terms and relevant laws.

7. Readiness and Willingness of the Petitioner to Perform Contractual Obligations:
The petitioner argued that they had invested significant funds and completed 34% of the work, demonstrating readiness and willingness to perform. The arbitrator found that the petitioner had not carried out any work since January 2011, had no funds, and their accounts were frozen by Vijaya Bank. The arbitrator concluded that the petitioner was not ready and willing to perform their obligations and upheld the termination of the agreements.

Conclusion:
The court upheld the arbitrator's decision, finding no merit in the petitioner's claims. The termination of the agreements was justified due to the petitioner's defaults, and the respondent was not obligated to issue a fresh counter guarantee. The allegations of fraud were dismissed, and the court emphasized that commercial contracts must be interpreted strictly according to their terms. The petition was rejected, and the request for continuation of the status quo order was denied.

 

 

 

 

Quick Updates:Latest Updates