Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2016 (2) TMI SC This

  • Login
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2016 (2) TMI 1284 - SC - Indian Laws


Issues Involved:
1. Determination of tariff for solar power projects.
2. Application of accelerated depreciation benefits under the Income Tax Act.
3. Interpretation of Power Purchase Agreement (PPA) clauses.
4. Applicability of the principle of promissory estoppel.

Detailed Analysis:

1. Determination of Tariff for Solar Power Projects:

The Gujarat Electricity Regulatory Commission (2nd respondent) issued the 1st Tariff Order on 29.01.2010, setting the tariff for solar power projects at Rs. 15 per kWh for the first 12 years and Rs. 5 per kWh for the subsequent 13 years. This tariff was based on various financial and operational parameters, including the benefit of accelerated depreciation under the Income Tax Act. A subsequent 2nd Tariff Order dated 27.01.2012 determined different tariffs for projects availing and not availing accelerated depreciation, with the latter being more favorable.

2. Application of Accelerated Depreciation Benefits:

The 1st respondent did not avail the accelerated depreciation benefits under Section 32 of the Income Tax Act. The 1st Tariff Order specified that projects not availing such benefits could seek a separate tariff determination. The 1st respondent commissioned its project on 2.3.2012, beyond the control period of the 1st Tariff Order, and sought the more favorable tariff under the 2nd Tariff Order.

3. Interpretation of Power Purchase Agreement (PPA) Clauses:

The PPA between the appellant and the 1st respondent, dated 09.12.2010, stipulated the tariff as per the 1st Tariff Order for projects commissioned on or before 31.12.2011. If commissioning was delayed, the tariff would be as determined by the Commission on the commissioning date or the previously mentioned tariff, whichever was lower. The 1st respondent entered into a Supplemental Agreement on 07.05.2011, but Articles 5.1 and 5.2 remained unaltered.

4. Applicability of the Principle of Promissory Estoppel:

The 2nd respondent and the Appellate Tribunal for Electricity ruled that the 1st respondent was entitled to the tariff under the 2nd Tariff Order. The appellant argued that the 1st respondent, having entered into the PPA, could not later opt out of the accelerated depreciation benefits and claim a different tariff. The principle of promissory estoppel was discussed but not applied, as the PPA recognized the possibility of different tariffs depending on the commissioning date and the project's benefits.

Judgment Summary:

The Supreme Court set aside the orders of the 2nd respondent and the Appellate Tribunal, ruling that the 1st respondent could not claim the more favorable tariff under the 2nd Tariff Order after entering into the PPA. The Court emphasized that the PPA clearly stipulated the applicable tariff in case of delayed commissioning and that the 1st respondent's right to seek a separate tariff should have been exercised before entering into the PPA. The appeal was allowed with costs of Rs. 2 lakhs payable by the 1st respondent. The Court also noted that the appeal raised substantial questions of law, justifying its jurisdiction under Section 125 of the Electricity Act.

 

 

 

 

Quick Updates:Latest Updates