Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2020 (10) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (10) TMI 1348 - HC - Indian Laws


Issues Involved:
1. Challenge to the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.
2. Application for condonation of delay in filing the petition challenging the arbitral award.

Detailed Analysis:

1. Challenge to the Arbitral Award:
The Southern Railways filed an Original Petition (O.P) on 14.10.2019 under Section 34 of the Arbitration and Conciliation Act, 1996 (A and C Act) to challenge an arbitral award dated 10.06.2019. The award was made by a sole arbitrator concerning disputes arising from a contract for gauge conversion work between Mayliaduthurai-Thiruvarur Railway Stations. The primary disputes involved reduction of vitiation amounts from running bills and the price variation clause.

2. Application for Condonation of Delay:
Southern Railways also filed an application (A.No.9150 of 2019) to condone a 30-day delay in filing the O.P. The key dates relevant to the delay are:
- Award made: 10.06.2019
- Award received by Southern Railways: 13.06.2019
- Prescribed period of three months starts: 14.06.2019
- High Court closed for Dussehra vacation: 05.10.2019 to 13.10.2019
- O.P filed: 14.10.2019

The Contractor resisted the application, arguing that the delay exceeded 30 days and was therefore not condonable under the proviso to sub-section (3) of Section 34 of the A and C Act.

Court's Analysis and Reasoning:
- The Court highlighted that applications under Section 34 of the A and C Act are termed as Original Petitions in this Court.
- It was undisputed that the three-month period should be computed from 14.06.2019, excluding the date of receipt of the award (13.06.2019), as per the Himachal Techno Engineers case.
- The Court noted that the prescribed period of three months ended on 13.09.2019. Southern Railways argued that the delay was due to the Dussehra vacation when the Court was closed, thus justifying the filing on the next working day, 14.10.2019.
- The Contractor contended that the benefit of Section 10 of the General Clauses Act, 1897 and Section 4 of the Limitation Act, 1963 applies only to the prescribed period of limitation and not to the further condonable period of 30 days.

Key Case Laws Cited:
- Simplex Infrastructure Limited Vs. Union of India: Emphasized that the expression "but not thereafter" in the proviso to Section 34(3) is crucial and delay beyond 30 days is not condonable.
- Popular Construction Company: Reinforced that the language of the proviso to Section 34(3) is strict and non-derogable.
- Himachal Techno Engineers: Clarified that the date of receipt of the award should be excluded when computing the three-month period.
- Assam Urban Water Supply: Stated that the benefit of the Court being closed applies only to the prescribed period of limitation and not to the further condonable period.

Conclusion:
- The Court concluded that the delay of even one day beyond 30 days is not condonable due to the strict language of the proviso to Section 34(3) of the A and C Act.
- The Court found that Southern Railways did not provide a convincing explanation for the delay, as the affidavit in support of the application was terse and lacked specificity.
- The Court emphasized the importance of adhering to strict timelines under the A and C Act to ensure expeditious resolution of disputes, a critical component of the Alternate Dispute Resolution (ADR) mechanism.

Final Order:
- The application for condonation of delay (A.No.9150 of 2019) was dismissed.
- Consequently, the Original Petition (O.P(D).No.128930 of 2019) was rejected as time-barred.
- There was no order as to costs.

 

 

 

 

Quick Updates:Latest Updates