Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2017 (8) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2017 (8) TMI 1712 - HC - Indian Laws


Issues Involved:
1. Alleged breach of contract by the petitioner.
2. Termination of the contract by the respondent.
3. Environmental damage allegations.
4. Applicability of Section 14(3)(c) of the Specific Relief Act, 1963.
5. Grant of injunction and specific performance of the contract.

Detailed Analysis:

1. Alleged Breach of Contract by the Petitioner:
The respondent accused the petitioner of failing to start the work on time and delaying the project. A letter dated 8th March 2017 from the Principal Secretary of the Tourism Department granted the petitioner six months to complete specific components of the project. The petitioner committed to finishing the items by 31st August 2017 and provided progress reports. However, on 8th June 2017, a show cause notice was issued alleging defaults such as no plantation for soil erosion, lack of safety officers, and absence of noise level monitoring, among others. The petitioner responded on 30th June 2017, addressing each allegation and attributing some responsibilities to state instrumentalities.

2. Termination of the Contract by the Respondent:
On 11th July 2017, the Director of Tourism issued a termination notice citing environmental concerns and other breaches. The petitioner argued that the termination notice was issued to render their application in-fructuous, as it was awaiting court consideration. The court noted that there was no prior indication of dissatisfaction with the petitioner's work and found the sudden environmental damage allegations extraordinary and unsupported by evidence.

3. Environmental Damage Allegations:
The termination notice accused the petitioner of activities endangering the environment, such as soil erosion, cutting trees for firewood, and lack of solid waste management. The court found these allegations suspicious and unsupported by evidence. It noted that there were no prior complaints about environmental damage before June 2017, and the petitioner's detailed response on 30th June 2017 was not adequately addressed by the respondent.

4. Applicability of Section 14(3)(c) of the Specific Relief Act, 1963:
The petitioner argued that the contract fell within the scope of Section 14(3)(c) of the Specific Relief Act, which allows specific performance for construction or other work on land if certain conditions are met. The court agreed, noting that the petitioner had a substantial interest in the land and project, and compensation in money would not be adequate. The contract was for 32 years, renewable for another 32 years, granting the petitioner exclusive possession and control over the island.

5. Grant of Injunction and Specific Performance of the Contract:
The court considered the principles governing the grant of injunctions and specific performance. It found that the petitioner had established a prima facie case, with the balance of convenience and irretrievable injury factors in their favor. The court noted that the contract was not determinable by nature, and damages would not be an adequate remedy. The contract was definable and capable of specific performance under court supervision.

Summary of Findings:
a) The petitioner was in firm possession of the land for 32 years, renewable for another 32 years, with substantial construction work already started.
b) The Principal Secretary's letter dated 8th March 2017 extended the time for completing the work until 7th September 2017.
c) The petitioner kept the respondent informed of the progress, with no disagreement from the respondent.
d) There were no allegations of environmental damage until June 2017.
e) The show cause notice dated 8th June 2017 raised environmental damage allegations.
f) The petitioner's detailed response on 30th June 2017 was not adequately addressed.
g) The Director of Tourism terminated the contract without the Principal Secretary's concurrence.
h) The environmental damage allegations were unsupported by evidence.
i) The petitioner was performing the work as expected.
j) The contract was not determinable by nature.
k) Damages were not an adequate remedy for breach of the contract.
l) The contract was capable of specific performance under court supervision.
m) The respondent was in breach of the contract, not the petitioner.
n) The pending application hindered the petitioner's progress.
o) The termination of the contract on 11th July 2017 was wrongful and illegal.

Order:
The termination notice dated 11th July 2017 was set aside. The respondent was restrained from terminating the contract until 7th September 2017 and for a further 45 days thereafter. The petitioner was entitled to resume work immediately, and the respondent was directed to cooperate. The Principal Secretary was instructed to ensure proper handling of the contract. The application was allowed.

 

 

 

 

Quick Updates:Latest Updates