Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2019 (5) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2019 (5) TMI 1216 - HC - Indian Laws


Issues Involved:
1. Maintainability of the reference case before the Bihar Public Works Contract Disputes Tribunal.
2. Applicability of the Arbitration and Conciliation Act, 1996 versus the Bihar Public Works Contracts Arbitration Tribunal Act, 2008.
3. Judicial propriety and judicial discipline in following Supreme Court decisions.
4. Interim protection for the petitioner.

Detailed Analysis:

Issue 1: Maintainability of the Reference Case Before the Bihar Public Works Contract Disputes Tribunal
The petitioner initially moved the Tribunal by filing a petition (Reference Case No. 341 of 2018) on 21.12.2018. However, the Tribunal observed that the reference case was not maintainable based on the Supreme Court's decision in Civil Appeal No. 3344 of 2018 (State of Bihar & Ors. v. M/S Brahmaputra Infrastructure Ltd.). The Supreme Court had ruled that the Arbitration and Conciliation Act, 1996 (Central Act) applies when there is an arbitration agreement stipulating its applicability, thus excluding the Bihar Public Works Contracts Arbitration Tribunal Act, 2008 (State Act).

Issue 2: Applicability of the Arbitration and Conciliation Act, 1996 Versus the Bihar Public Works Contracts Arbitration Tribunal Act, 2008
The petitioner argued that the State Arbitral Tribunal is competent to adjudicate disputes arising from the agreement. They cited the Supreme Court's judgment in Madhya Pradesh Rural Road Development Authority & Anr. v. L.G. Chaudhary Engineers and Contractor, which held that state laws on arbitration could prevail if they have received presidential assent and are not repugnant to the Central Act. The Bihar Act, 2008, however, had not received presidential assent, and Section 8 of the Bihar Act stated that in case of conflict, the Central Act would prevail. Therefore, the Central Act was applicable.

Issue 3: Judicial Propriety and Judicial Discipline in Following Supreme Court Decisions
The court acknowledged the need to follow the Supreme Court's decisions for judicial propriety and discipline. The Supreme Court’s judgment in M/S Brahmaputra Infrastructure Ltd. was considered authoritative, stating that the Central Act applies when an arbitration agreement stipulates its applicability, and the Bihar Act, 2008 does not apply in such cases. The court found no inconsistency between this judgment and the one in Madhya Pradesh Rural Road Development Authority, as the latter involved a state act with presidential assent, unlike the Bihar Act.

Issue 4: Interim Protection for the Petitioner
The court extended the interim protection granted to the petitioner in earlier orders for eight weeks, allowing the petitioner to seek appropriate remedies under the law without prejudice.

Conclusion:
The court concluded that the agreement in question, governed by the Standard Bidding Document and Clause-25 of the General Condition of Contract, mandates arbitration under the Arbitration and Conciliation Act, 1996. Consequently, the Bihar Public Works Contracts Arbitration Tribunal Act, 2008 does not apply. The court recalled its earlier order directing the petitioner to move the Bihar Public Works Contract Disputes Arbitration Tribunal and granted the petitioner liberty to seek remedy under the Arbitration and Conciliation Act, 1996. The review petition was allowed, and interim protection was extended to the petitioner for eight weeks.

 

 

 

 

Quick Updates:Latest Updates