Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2020 (2) TMI SC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (2) TMI 679 - SC - Indian Laws


Issues Involved:

1. Legitimacy of the Arbitrator's Award for Claim Nos. 2, 3, 8, 12, and 16.
2. Requirement for the Arbitrator to provide reasons for the Award.
3. Calculation of premium rates for extra work.
4. Adherence to contractual provisions for submitting claims.
5. Grant of interest on awarded amounts.

Detailed Analysis:

1. Legitimacy of the Arbitrator's Award for Claim Nos. 2, 3, 8, 12, and 16:

The appellant challenged the High Court's partial acceptance of Claim No. 1 and rejection of other claims. The contract involved construction work with an estimated cost of ?31 lakhs and a contract amount of ?59,86,732. The claimant sought additional payment due to increased scope of work. The Arbitrator awarded the claimed amounts with 18% interest, which was partially modified by the Sub-Judge and further by the District Judge, leading to the appellant's revision petition.

2. Requirement for the Arbitrator to Provide Reasons for the Award:

The contract's Clause 63 mandated that Awards exceeding ?1 lakh must state reasons. The Arbitrator's Award for Claim No. 2 merely stated, "As per agreement premium works out to 93.12% which is awarded," without providing detailed reasoning. The First Appellate Court and High Court found this insufficient, emphasizing the need for reasons as per the contract.

3. Calculation of Premium Rates for Extra Work:

The claimant argued for a premium of 93.12%, based on the difference between the estimated cost and the contract amount. The opposite party contended that the premium should be 35.02%, as per the communication dated 05.01.1987. The courts concluded that the Arbitrator's Award lacked justification for the 93.12% premium and did not adhere to the contract's provisions. The Supreme Court concurred, directing the premium to be calculated at 35.02%.

4. Adherence to Contractual Provisions for Submitting Claims:

Claim No. 8 involved extra work on marshy land (DALDAL). The contract required monthly returns for extra work claims, which the claimant failed to submit. The First Appellate Court and High Court rejected the claim based on this non-compliance. The Supreme Court, however, held that outright rejection was too technical, recognizing the actual work done and directing the premium to be calculated at 35.02%.

5. Grant of Interest on Awarded Amounts:

The Arbitrator awarded 18% interest, which was reduced to 12% by the Sub-Judge and upheld by the High Court. The Supreme Court found the 12% interest appropriate, given the absence of an agreed rate.

Conclusion:

The Supreme Court modified the orders of the First Appellate Court and High Court, directing that in addition to Claim No. 1, the claimant is entitled to amounts under Claim Nos. 2, 3, 8, and 12, calculated at a premium of 35.02% with 12% interest per annum. This calculation and payment must be completed within six weeks, failing which the interest rate will increase to 18% per annum. The appeal was allowed in part, and the Registry was directed to draw up the decree/award accordingly.

 

 

 

 

Quick Updates:Latest Updates