Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Service Tax Service Tax + AT Service Tax - 2021 (2) TMI AT This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (2) TMI 790 - AT - Service Tax


Issues:
1. Construction of Complex Service demand
2. Service Tax under site formation, clearance, excavation, and earthmoving
3. Works Contract Service demand
4. Erection, Commissioning, and Installation Service demand
5. Contested Service Tax demand
6. Imposition of penalty under Section 78

Construction of Complex Service demand:
The appellant contested the demand related to Construction of Complex Service (CCS) for the period from 2006-07 to 2009-10. The appellant argued that the demand was raised in connection with residential apartments constructed under a tripartite agreement. The Tribunal found that the appellant was involved in providing taxable services under CCS, including construction of residential complexes. The Tribunal noted that the appellant undertook further construction activities to complete semi-finished flats into residential units, which fell outside the exclusion clause. The demand was not sustainable as the law required that such complexes should not be constructed by a person engaging others for designing or planning, a requirement met by the appellant.

Service Tax under site formation, clearance, excavation, and earthmoving:
The appellant did not contest the demand for Service Tax under site formation and related services for the period from 2009-10 to 2010-11. However, the appellant disputed the imposition of equal penalty under Section 78. The Tribunal observed that the penalty was levied without verifying the presence of the necessary ingredients under Section 78. The appellant's belief that the work was not liable to Service Tax due to its nature was considered bona fide. The penalty was deemed unjustified, and the demand could not sustain.

Works Contract Service demand:
The demand under Works Contract Service (WCS) for the Pranahitha Chevella Lift Irrigation Project was contested by the appellant. The Tribunal referred to a precedent and concluded that the demand could not be sustained. The appellant's activities in completing the project before handing it over aligned with the precedent's interpretation of WCS. Hence, the demand under WCS was not justified.

Erection, Commissioning, and Installation Service demand:
Regarding the demand under Erection, Commissioning, and Installation Service (ECIS), the appellant argued that the works did not fall under the commercial or industrial purpose category. The Tribunal agreed with the appellant's contentions, citing relevant judgments. The demand on this count was deemed unsustainable.

Contested Service Tax demand:
The Service Tax demand, not disputed by the appellant, was paid along with interest. The appellant contested the levy of penalty under Section 78 on the grounds of bona fides. The Tribunal found merit in the appellant's arguments, leading to the conclusion that the penalty could not be sustained.

Imposition of penalty under Section 78:
The Tribunal analyzed the imposition of penalty under Section 78, emphasizing the necessity for tax evasion or non-compliance with the Act due to fraud or wilful suppression. The Tribunal found no evidence of wilful evasion by the appellant and noted the absence of any findings against the appellant. The penalty was considered unjustified, especially in the absence of fraud or misrepresentation. Consequently, the penalty imposed on the appellant was deleted.

This detailed analysis of the judgment addresses the various issues involved in the case, highlighting the arguments presented by both parties and the Tribunal's reasoning for each issue.

 

 

 

 

Quick Updates:Latest Updates