Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Insolvency and Bankruptcy Insolvency and Bankruptcy + AT Insolvency and Bankruptcy - 2022 (1) TMI AT This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2022 (1) TMI 403 - AT - Insolvency and Bankruptcy


Issues Involved:
1. Pre-existing dispute between the parties.
2. Admissibility of the application under Section 9 of the IBC.
3. Violation of the agreement/contract and its implications.
4. Determination of the amount due and payable.

Issue-wise Detailed Analysis:

1. Pre-existing dispute between the parties:
The primary issue revolves around whether there was a pre-existing dispute between the parties before the demand notice was issued. The Adjudicating Authority observed that there were clear indications of a pre-existing dispute related to the quality and delivery of coal. The Operational Creditor (OC) refused to accept the coal due to alleged inferior quality and non-delivery through a specific vessel, which the Corporate Debtor (CD) countered by alleging the OC's failure to lift the coal and delayed payments. The Tribunal noted that these allegations and counter-allegations proved the existence of a pre-existing dispute.

2. Admissibility of the application under Section 9 of the IBC:
The Tribunal emphasized that for an application under Section 9 of the IBC to be admitted, there should not be any pre-existing dispute. The Tribunal referred to the Supreme Court's judgments in "Innoventive Industries Ltd. Vs. ICICI Bank" and "Mobilox Innovations Pvt. Ltd. Vs. Kirusa Software Pvt. Ltd." to highlight that the existence of a dispute, even if raised before the demand notice, is sufficient to reject the application. The Tribunal found that the dispute between the parties was genuine and not spurious, thus making the application inadmissible.

3. Violation of the agreement/contract and its implications:
The Tribunal discussed the alleged breach of the agreement dated 27.02.2019 between the parties. The OC claimed that the CD failed to deliver the agreed quantity of coal and did not refund the advance payment. However, the CD argued that the agreement was inconclusive and pointed out that the OC had not fulfilled its obligations. The Tribunal noted that the determination of whether there was a breach of contract requires a detailed investigation, which cannot be conducted in a summary proceeding under the IBC.

4. Determination of the amount due and payable:
The OC claimed an outstanding amount of ?2,22,38,286/- including interest. The CD, however, contested this amount, stating that it had supplied 1476.36 MT of coal and that the remaining quantity was sold due to the OC's failure to lift it. The Tribunal observed that the calculation of the exact amount due involved complex issues that needed to be resolved in a proper legal forum, not in a summary proceeding under the IBC.

Conclusion:
The Tribunal concluded that the application under Section 9 of the IBC was rightly dismissed by the Adjudicating Authority due to the existence of a pre-existing dispute. The Tribunal emphasized that the IBC is not meant for resolving contractual disputes and that such matters should be adjudicated in appropriate legal forums. The appeal was dismissed without costs, and the application for exemption to file a certified copy of the impugned order was closed.

 

 

 

 

Quick Updates:Latest Updates