2014 (4) TMI 1323 - HC - Companies Law


Issues:
1. Breach of contract and failure to deliver possession of the apartment within the stipulated time frame.
2. Dispute over the amount paid by the petitioner and the balance amount claimed by the respondent.
3. Allegation of inability to repay debts and the petition for winding up.

Analysis:
1. The petitioner alleged breach of contract by the respondent for failing to deliver possession of the apartment within the agreed timeframe. The respondent claimed delays were due to unavoidable circumstances and that the agreement allowed for extensions in such cases. The respondent argued that the contract was not subject to termination but only attracted damages. The petitioner demanded a refund with interest, alleging misuse of funds by the respondent, leading to the winding up petition.

2. Dispute arose over the amount paid by the petitioner and the balance claimed by the respondent. The petitioner made payments totaling Rs. 50,25,954/- as per the Construction Agreement. The respondent contended that a balance of Rs. 11,68,600/- was due, considering the total cost of the apartment. The respondent also mentioned additional expenses not covered by the payments made by the petitioner, disputing the existence of a crystallized debt.

3. The respondent proposed a settlement by repaying the remaining amount with interest at 10%. The petitioner argued that the lack of interest payment on the substantial sum already paid raised concerns about the respondent's ability to meet its commitments. The court directed the respondent to pay interest on the amount already paid and concluded that the respondent could meet its obligations, dismissing the winding up petition.

In conclusion, the court found that the respondent's proposed repayment plan, along with the additional interest directed by the court, demonstrated the respondent's ability to meet its commitments. The court dismissed the winding up petition based on the satisfaction that the respondent could repay the outstanding amount as proposed, including the interest on the amount already paid.

 

 

 

 