Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2024 (8) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2024 (8) TMI 387 - HC - Indian Laws


Issues Involved:
1. Payment of interest from 1 July 2016 to 31 December 2019.
2. Exclusion of the COVID-19 pandemic period for interest liability.

Issue-Wise Detailed Analysis:

1. Payment of Interest from 1 July 2016 to 31 December 2019:
The primary contention revolves around whether the promoter (Appellant) should pay interest to the flat purchasers (Respondents) from 1 July 2016. The Appellant argued that the interest should only be calculated from 1 January 2020, based on an order dated 4 July 2018 by MahaRERA, where the Respondents had agreed to take possession by 31 December 2019 without claiming interest. However, the Tribunal emphasized that the possession was not handed over by 31 December 2019, making the debate over the 4 July 2018 order academic. The Tribunal held that the date of completion mentioned in the project registration under Section 4(2)(l)(C) of RERA does not alter the original agreement terms. The Tribunal cited the judgment in Neelkamal Realtors Suburban Pvt. Ltd. Vs. Union of India, which clarified that RERA does not rewrite contracts between promoters and flat purchasers. Thus, the Tribunal directed the Appellant to pay interest from 1 July 2016, as the original agreement specified possession by 30 June 2016.

2. Exclusion of the COVID-19 Pandemic Period for Interest Liability:
The Appellant sought exemption from paying interest during the COVID-19 lockdown period, citing Order No. 21 of 2022 and a Circular dated 6 August 2021. However, the Tribunal dismissed this appeal, noting that the Appellant had committed to handing over possession by 31 December 2019, well before the pandemic. The Tribunal found that the Appellant's failure to meet this deadline precluded them from claiming relief based on the pandemic. The Tribunal further noted that the Appellant had not initially challenged the MahaRERA's order but only filed an appeal after the Respondents' appeal was heard. The Tribunal concluded that the Appellant could not use the pandemic as an excuse to avoid interest liability.

Additional Observations:
The Tribunal also addressed the Appellant's conduct post-issuance of the Occupancy Certificate on 27 April 2022. The Appellant's insistence on additional payments and refusal to adjust the interest payable as per the MahaRERA's order was deemed unreasonable. The Tribunal held that the Appellant's actions indicated a disinclination to hand over possession, thereby justifying continued interest liability until possession is delivered.

Conclusion:
The Tribunal found no substantial question of law in the Appellant's appeals and rejected them. The Appellant was directed to immediately hand over possession of the flat to the Respondents to stop the accruing interest liability. The Respondents were allowed to withdraw the amount deposited by the Appellant in the RERA Appellate Tribunal, along with accrued interest. The Tribunal emphasized that the amount of interest payable now exceeds the balance amount, taxes, and charges payable by the Respondents, necessitating the immediate handover of possession.

 

 

 

 

Quick Updates:Latest Updates