Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases IBC IBC + AT IBC - 2025 (2) TMI AT This

  • Login
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2025 (2) TMI 1061 - AT - IBC


ISSUES PRESENTED and CONSIDERED

The primary issue considered in this judgment is whether the delay of 104 days in refiling the appeal by the Appellant should be condoned under the provisions of the National Company Law Appellate Tribunal Rules, 2016, and the Insolvency and Bankruptcy Code, 2016 (IBC). The core legal question revolves around whether the Appellant has demonstrated sufficient cause for the delay in refiling the appeal, considering the statutory limitations and the principles established in relevant precedents.

ISSUE-WISE DETAILED ANALYSIS

Relevant Legal Framework and Precedents

The legal framework for condoning delays in refiling appeals is governed by the National Company Law Appellate Tribunal Rules, 2016, particularly Rule 14, which allows for exemption from compliance with procedural requirements if sufficient cause is shown. The IBC, being a time-bound mechanism, emphasizes the need for expeditious proceedings, and the statutory limitations under Section 61(2) of the IBC prescribe specific time limits for filing appeals.

The Appellant cited various judgments to support the argument that the Tribunal has the power to condone delays in refiling appeals, including precedents where delays were condoned due to sufficient cause. These included cases like Indian Statistical Institute Vs. Associated Builders & Ors., and others where procedural delays were excused under specific circumstances.

Court's Interpretation and Reasoning

The Tribunal acknowledged its power to condone delays in refiling appeals but emphasized that such power must be exercised within the statutory limitations and only when sufficient cause is demonstrated. The Tribunal noted that the IBC proceedings are designed to be completed within a stringent timeline, and any delay must be justified with reasonable and justifiable cause.

Key Evidence and Findings

The Appellant argued that the delay was due to the illness of the counsel's father, who suffered a brain stroke in September 2024, and other procedural and technical issues. However, the Tribunal found that there was a lack of action from July to September 2024, which was not adequately explained. The Tribunal noted that there were other advocates on record who could have addressed the defects, indicating negligence on the part of the Appellant.

Application of Law to Facts

The Tribunal applied the principles from relevant precedents, such as Govardhan Nirman Pvt. Ltd. v. Vaibhav Khandelwal and Anr., which emphasized that the delay in refiling can only be condoned if reasonable and justifiable cause is shown. The Tribunal found that the Appellant failed to provide a convincing explanation for the delay, particularly for the period from July to September 2024, and thus did not meet the necessary threshold for condonation.

Treatment of Competing Arguments

The Tribunal considered the Appellant's reliance on judgments that condoned delays due to counsel's mistakes and procedural issues. However, it concluded that these precedents were not applicable to the present case due to the lack of reasonable diligence and the failure to provide a satisfactory explanation for the entire period of delay.

Conclusions

The Tribunal concluded that the Appellant did not demonstrate sufficient cause for the delay in refiling the appeal, and the reasons provided were inadequate to justify the 104-day delay in the context of the IBC's time-bound proceedings.

SIGNIFICANT HOLDINGS

The Tribunal held that:

"The delay of 104 days in refiling is not reasonable and justifiably explained. The application is therefore dismissed." This holding underscores the principle that procedural delays must be justified with sufficient cause, especially in time-sensitive proceedings under the IBC.

The Tribunal reiterated the importance of adhering to the statutory timelines under the IBC, emphasizing that procedural laws should not be used to defeat substantive justice but must be balanced with the need for timely resolution of insolvency proceedings.

In conclusion, the Tribunal dismissed the application for condonation of delay and consequently dismissed the appeal, reinforcing the strict adherence to procedural timelines in insolvency proceedings.

 

 

 

 

Quick Updates:Latest Updates