Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + SC Companies Law - 2013 (11) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2013 (11) TMI 632 - SC - Companies Law


Issues Involved:
1. Validity of Clause 29 and similar clauses as arbitration agreements.
2. Interpretation of arbitration clauses in various contracts.
3. Jurisdiction and role of the Chief Engineer or designated officer in dispute resolution.
4. Applicability of previous judgments and legal precedents to the current cases.

Issue-wise Detailed Analysis:

1. Validity of Clause 29 and Similar Clauses as Arbitration Agreements
The primary issue in the appeals was whether Clause 29 and similar clauses in the contracts constituted arbitration agreements. The Supreme Court held that Clause 29 and similar clauses did not constitute arbitration agreements. The clauses were deemed to be departmental dispute resolution mechanisms rather than arbitration clauses. The Court emphasized that the Chief Engineer or designated officer was not an independent authority and was not required to adjudicate disputes in a judicial manner.

2. Interpretation of Arbitration Clauses in Various Contracts
The Court analyzed various clauses from different contracts to determine if they constituted arbitration agreements. For example, Clause 29(a) required disputes to be referred to the Chief Engineer, whose decision was binding on the contractor but could be challenged in a court of law. Similar clauses in other contracts were also examined, such as Clause 7, Clause 66, and Clause 67, which had similar provisions for dispute resolution by a designated officer or engineer.

3. Jurisdiction and Role of the Chief Engineer or Designated Officer in Dispute Resolution
The Court discussed the role of the Chief Engineer or designated officer in dispute resolution. It was noted that these officers were not independent arbiters but were part of the departmental hierarchy with supervisory roles. Their decisions were not final and binding in the sense required for arbitration awards, as they could be challenged in court. The Court highlighted the principle that a person cannot be a judge in their own cause, which applied to these officers.

4. Applicability of Previous Judgments and Legal Precedents to the Current Cases
The Court reviewed several previous judgments to determine their applicability to the current cases. It referred to judgments such as Mysore Construction Company v. Karnataka Power Corporation Ltd., State of U.P. v. Tipper Chand, and State of Orissa v. Damodar Das, which supported the view that clauses like Clause 29 did not constitute arbitration agreements. The Court also distinguished the current cases from other judgments where clauses were interpreted as arbitration agreements, such as Punjab State v. Dina Nath and Krishna Bhagya Jala Nigam Ltd. v. G. Harishchandra Reddy, based on the specific wording and context of the clauses.

Conclusion:
The Supreme Court dismissed the appeals challenging the rejection of applications for the appointment of arbitrators under Clause 29 and similar clauses, affirming that these clauses did not constitute arbitration agreements. The Court allowed the appeals filed by Karnataka Neeravari Nigam Limited and Krishna Bhagya Jala Nigam Limited, setting aside the orders directing the Chief Engineer to act as an arbitrator. The parties were given the liberty to seek appropriate legal remedies for recovery of amounts due.

 

 

 

 

Quick Updates:Latest Updates