Turnkey EPC Contract are not getting covered under supply of ...


Turnkey EPC Contract for Solar Plant Not a 'Solar Power Generating System' Under Entry 234; Taxed at 18% as Works Contract.

September 13, 2018

Case Laws     GST     AAR

Turnkey EPC Contract are not getting covered under supply of 'Solar Power Generating System' under Entry 234 of Schedule I of the Notification - The contract for Erection, Procurement and Commissioning of Solar Power Plant falls under the ambit “Works Contract Services” - attracts 18% rate of tax

View Source

 


 

You may also like:

  1. Rate of GST - product Solar HT/LT XLPE Cables to be used in the manufacture of Solar Power Generating System/ Solar Power Generator - The product in question viz. Solar...

  2. Classification of Supply - supply of solar power generating system - Turnkey EPC Contract - split contract for supply of goods and supply of services may not be valid -...

  3. Input tax credit - inputs / capital goods / input services - Solar Power Generating Plant of the applicant qualify as 'plant and machinery' as it falls under machinery -...

  4. Rate of tax - supply and setting up of ‘solar power generating system’ - Supply of the said turnkey EPC contract is a ‘composite supply’ u/s.2(30) of the CGST Act, 2017....

  5. The HC held that the supply of a Solar Power Generating System by the petitioner is a composite supply and does not amount to a works contract u/s 2(119) of the GST Act....

  6. Classification of Service - Rate of GST - turnkey Engineering, Procurement and Construction (EPC) Contract for construction of a solar power plant - cannot be held as...

  7. Supply of solar inverter, controller, battery and panels would covered under “Solar Power Generating System” as a whole in terms of serial no. 234 of Schedule-I of the...

  8. Disallowance of higher reduction of depreciation on the cost of civil engineering works for laying foundation of solar power panels - the expenditure which is incurred...

  9. Works Contract Service - Turnkey Contract - What matters is the fact that the contracts were executed by the appellants and payments received by them after 01/06/2007...

  10. Supply of turnkey Engineering, Procurement & Construction (EPC) Contract for construction of a solar power plant - Nature of supplies made by sub-contractors - the...

  11. Classification of goods and rates of GST - solar inverter - the combination of solar panel, inverter, solar battery and charge controller may qualify as “Solar Power...

  12. Composite supply - natural bundling - The supply of the PV module which is the major component of the Solar Power Plant is not naturally bundled with the supply of the...

  13. Classification - Substation Equipments - part of “Solar Power Generating System” or not - Once the entry includes “Solar Power Project”, all the material equipments used...

  14. Classification of supply - GST rate - the activities of supply, design, installation, commissioning and testing of solar energy based water pumping systems, whose time...

  15. Irregular availment of CENVAT Credit - input services - transport service of Fly Ash - The removal of coal Fly Ash is one of the necessity for running of the captive...

 

Quick Updates:Latest Updates