Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 1979 (1) TMI SC This

  • Login
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

1979 (1) TMI 229 - SC - Indian Laws


Issues Involved:
1. Whether time was of the essence of the contract.
2. Whether the rescission of the contract by the respondent-defendant was wrongful and illegal.
3. Entitlement of the appellant-plaintiff to damages and refund of the security deposit.

Issue-wise Detailed Analysis:

1. Whether time was of the essence of the contract:
The court examined whether the 12-month period specified for the completion of the aqueduct construction was fundamental to the contract. The contract, executed on July 12, 1955, stipulated that the work should commence on July 5, 1955, and be completed by July 4, 1956. The appellant-plaintiff contended that the time period was not of the essence, citing the nature of construction contracts and the inclusion of clauses for extension of time and penalties for delays. The court noted that the contract included provisions for extension of time (Clause 6) and penalties for delays (Clause 2), which indicated that the parties did not intend for the 12-month period to be fundamental. The court concluded that time was not of the essence of the contract, and the stipulated period had been waived by the respondent-defendant.

2. Whether the rescission of the contract by the respondent-defendant was wrongful and illegal:
The court analyzed whether the respondent-defendant's rescission of the contract on August 27, 1956, was justified. The appellant-plaintiff argued that the rescission was wrongful as the respondent-defendant did not grant a reasonable extension of time despite the appellant-plaintiff's requests. The court found that the appellant-plaintiff had requested an extension of time before the expiry of the initial 12-month period, and the refusal to grant an extension was unreasonable. The court held that the respondent-defendant should have fixed a new period making time the essence and only rescind the contract if the appellant-plaintiff failed to complete the work within that period. The court concluded that the rescission was wrongful and illegal, constituting a breach of contract by the respondent-defendant.

3. Entitlement of the appellant-plaintiff to damages and refund of the security deposit:
Given the wrongful rescission of the contract, the court examined the appellant-plaintiff's entitlement to damages and the refund of the security deposit. The trial court had awarded the appellant-plaintiff a refund of the security deposit of Rs. 4,936/-, Rs. 5,845/- for work done under Bill No. 1253, and nominal damages of Rs. 120/-. The High Court had modified this decree, upholding the forfeiture of the security deposit and awarding only Rs. 5,845/- for the work done. The Supreme Court found that the trial court's decision was correct, as the rescission was wrongful and the appellant-plaintiff was entitled to a refund of the security deposit and the amount for the work done. The court restored the trial court's decree, awarding the appellant-plaintiff Rs. 10,901/- with interest and costs.

Conclusion:
The Supreme Court allowed the appeal, set aside the High Court's judgment in F.A. No. 844 of 1961, and restored the trial court's decree. The appellant-plaintiff was awarded Rs. 10,901/- with interest and costs, confirming that the rescission of the contract by the respondent-defendant was wrongful and illegal. The High Court's decree dismissing F.A. No. 245 of 1962 was confirmed.

 

 

 

 

Quick Updates:Latest Updates