Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2012 (5) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2012 (5) TMI 764 - SC - Indian Laws


Issues Involved:
1. Eligibility of the successful bidder (Respondent No.2) regarding submission of certified balance-sheets for the last five years.
2. Experience of the successful bidder (Respondent No.2) in executing a single integrated water supply scheme of the requisite value.

Detailed Analysis:

1. Eligibility of the Successful Bidder Regarding Submission of Certified Balance-Sheets:

The appellant challenged the eligibility of Respondent No.2 on the grounds that the latter had not filed the requisite certified balance-sheets for the five years immediately preceding the issue of the tender notice. Respondent No.2 had submitted certified copies of audited balance-sheets for four years but provided a Chartered Accountant's certificate for the fifth year (2010-2011), as the audit for that year was not completed. The High Court held that this constituted substantial compliance with the NIT requirements, noting that the appellant did not dispute the correctness of the turnover certified for 2010-2011 or that it met the tender notice requirements. The Supreme Court found no legal flaw in this reasoning, emphasizing that the appellant had not demonstrated any incorrectness in the submitted documents. Thus, the first limb of the challenge was rejected.

2. Experience of the Successful Bidder in Executing a Single Integrated Water Supply Scheme:

The appellant argued that Respondent No.2 lacked the requisite experience, as the works executed at Vyara and Songadh were distinct and did not constitute a single integrated water supply scheme. Furthermore, the appellant contended that the Upleta project executed by Respondent No.2 did not include the construction of intake wells, an essential component of an integrated water supply scheme. The respondents countered that the Upleta project included all necessary components, and the High Court found that the nature of the work executed by Respondent No.2 satisfied the tender notice requirements. The Supreme Court agreed, noting that the Municipal Council had the aid of a technical consultant in evaluating the bids and determining eligibility. The Court found no reason to interfere with the High Court's view, as the evaluation process was neither irrational nor arbitrary.

Public Interest Consideration:

The Supreme Court highlighted that Respondent No.2 had already executed a significant portion of the contract and that interference at this stage would delay the project, adversely affecting the residents of the scarcity-stricken municipality. The project, aimed at providing drinking water, was funded under a Central Government scheme with a completion target of September 2012. The Court emphasized that public interest would be best served by allowing the project to proceed without further delays.

Conclusion:

The Supreme Court concluded that there was no mala fide or arbitrariness in the evaluation process and the determination of eligibility. The appeal was dismissed with costs assessed at Rs. 25,000, emphasizing the need for judicial restraint in administrative actions and the importance of public interest in such cases.

 

 

 

 

Quick Updates:Latest Updates