Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + SC Companies Law - 2015 (1) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2015 (1) TMI 16 - SC - Companies Law


Issues involved:
1. Arbitrability of disputes specifically excepted in the contract.
2. Authority of the Arbitrator to decide disputes not arbitrable.

Detailed Analysis:
1. The judgment concerns a dispute arising from a construction contract for a road bridge. The key issue revolves around whether an Arbitrator can arbitrate on disputes explicitly excepted in the contract. The contract contained Clause 63, which specified certain disputes as "excepted matters" not subject to arbitration.

2. The contractor was dissatisfied with the amount payable for extra work done, as per Clause 39 of the contract. The disputes included determining rates for additional work not covered in the contract. The Arbitrator, a former Judge, decided on all disputes, including those objected to by the contractor as non-arbitrable under Clause 39.

3. The contractor challenged the Arbitrator's decision, claiming that disputes under Clause 39 were not arbitrable. The City Civil Court set aside the Arbitration Award, leading to an appeal before the High Court. The High Court upheld the dismissal, prompting the contractor to file an appeal before the Supreme Court.

4. The Supreme Court analyzed the clauses in the contract, emphasizing that disputes identified in Clause 39 as "excepted matters" were non-arbitrable. The Court noted that unresolved disputes, such as determining payment for extra work, were not finalized by the Chief Engineer, rendering them non-arbitrable.

5. The Court highlighted that for disputes to be arbitrable, they must be explicitly included in the contract as per Section 7(3) of the Arbitration and Conciliation Act, 1996. The Court concluded that the Arbitrator exceeded authority by deciding on non-arbitrable disputes, as parties did not agree to refer such disputes for arbitration.

6. Ultimately, the Supreme Court partially allowed the appeal, quashing the Arbitrator's decision on non-arbitrable disputes but upholding arbitrable issues. The Court set aside the determination of rates for extra work, allowing the contractor to pursue legal action for payment recovery concerning work not covered in the contract.

 

 

 

 

Quick Updates:Latest Updates