Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2020 (8) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (8) TMI 955 - HC - Indian Laws


Issues Involved:

1. Jurisdiction of the arbitral tribunal in the absence of an arbitration clause.
2. Awarding compensation for delay, idling charges, and hire charges without specific contractual clauses.
3. Legality of the interest rate awarded.
4. Awarding interest on the interest component.

Detailed Analysis:

1. Jurisdiction of the Arbitral Tribunal:

The appellant raised a preliminary objection regarding the arbitral tribunal's jurisdiction, arguing that there was no arbitration clause in the agreement. The court referred to the Supreme Court's decision in SBP & Co. v. Patel Engg. Ltd., which established that the Chief Justice or designated Judge has the authority to decide on the existence of a valid arbitration agreement. In this case, the designated judge had already ruled on the existence of the arbitration clause, and the appellant did not challenge this decision in the Supreme Court. Therefore, the arbitral tribunal had jurisdiction, and the award could not be set aside on this ground.

2. Compensation for Delay, Idling Charges, and Hire Charges:

The appellant contended that the arbitral tribunal awarded compensation beyond the terms of the contract, as there were no clauses for price escalation or compensation for delay. The court cited precedents, including K.N. Sathyapalan v. State of Kerala, which allow compensation for extra costs incurred due to one party's failure to fulfill contractual obligations, even in the absence of specific clauses. The tribunal found that the delay was due to the appellant's lack of promptness, justifying the compensation awarded. The court upheld the tribunal's decision, stating that it was within its jurisdiction to award such compensation.

3. Legality of the Interest Rate Awarded:

The arbitral tribunal awarded interest at 12% per annum from 20.05.2010 to 14.10.2011. The appellant argued that this rate was excessive. The court noted that the tribunal did not provide reasons for this rate, and compared it to statutory amendments and other judicial precedents, suggesting that 12% was indeed high. Consequently, the court reduced the interest rate to 9% per annum for the specified period.

4. Awarding Interest on the Interest Component:

The appellant challenged the legality of awarding interest on the interest component of Rs. 10,40,105/-. The court referred to Section 31(7) of the Arbitration and Conciliation Act, which allows interest on the total sum awarded, including interest. The Supreme Court's decision in Hyder Consulting (UK) Ltd. v. Governor, State of Orissa supported this interpretation. Thus, the court found no illegality in awarding interest on the interest component.

Conclusion:

The court modified the arbitral award by reducing the interest rate from 12% to 9% per annum for the period from 20.05.2010 to 14.10.2011, adjusting the interest component accordingly. The appeal was disposed of with each party bearing its own litigation costs. The court directed that a copy of the judgment be sent to the lower court.

 

 

 

 

Quick Updates:Latest Updates