Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2015 (2) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2015 (2) TMI 1303 - HC - Indian Laws


Issues Involved:
1. Extension of concession period due to extra work and damages.
2. Suspension of toll collection during specific periods.
3. Responsibility for project delay.
4. Compensation claims for various heads including overheads, productivity loss, price escalation, subsequent legislation, royalty charges, excess excavation, and additional work.
5. Interest and costs awarded.

Detailed Analysis:

1. Extension of Concession Period Due to Extra Work and Damages:
The arbitration petitions arose from awards passed by an arbitral tribunal regarding a Build, Operate and Transfer (BOT) contract for road construction. The contractor, Atlanta, claimed an extension of the concession period due to extra work and damages. The State challenged the arbitral tribunal's award, which partly allowed Atlanta's claims and awarded Rs. 58,59,31,595 with interest at 20% per annum. The tribunal directed the State to extend the concession period based on Atlanta's cash flow statement or pay the awarded sum with interest.

2. Suspension of Toll Collection During Specific Periods:
The second reference involved Atlanta's claims for compensation due to the suspension of toll collection by the State during specific periods. The tribunal accepted Atlanta's claims and awarded Rs. 14,92,38,050 with interest. The State challenged this award, but the tribunal found that the suspension was not justified under the BOT contract, which did not provide for toll suspension as a remedy for maintenance issues.

3. Responsibility for Project Delay:
The tribunal examined the causes of project delay, attributing it to breaches by the State, including failure to hand over land, non-removal of encroachments, and additional work orders. The tribunal split the contract period into three phases and found that Atlanta was not responsible for the delays, which were caused by the State's breaches.

4. Compensation Claims for Various Heads:
- Extra Overheads and Loss of Expected Profit: The tribunal awarded Rs. 8,80,00,000 based on a 20% rate of overheads and profit, supported by evidence, trade practices, and the National Highway Authority of India's norms.
- Reduced Productivity of Plant and Machinery: The tribunal awarded Rs. 4,94,27,000 for idling machinery, but this was found unsustainable due to lack of evidence for the entire extended period.
- Reimbursement for Escalation in Prices: The tribunal awarded Rs. 16,95,47,000 for escalation in prices of materials, justified by the principle that contractors are entitled to compensation for extra expenses due to delays caused by the employer.
- Compensation Due to Subsequent Legislation: The tribunal awarded Rs. 8,38,61,595 for Minimum Alternate Tax (MAT) imposed after the contract, but this was found unjustified as the contract did not guarantee perpetuation of tax concessions.
- Reimbursement of Royalty Charges: The tribunal awarded Rs. 1,96,18,000 for royalty charges, but this was found unsustainable as the contract did not provide for compensation due to subsequent changes in law.
- Excess Excavation Work: The tribunal awarded Rs. 7,16,62,000 for extra excavation due to landslides, supported by bilateral measurement books and certificates.
- Difference in Rates for Additional Work: The tribunal awarded Rs. 10,38,16,000 for additional work, based on a reasonable interpretation of the contract and supported by evidence.

5. Interest and Costs Awarded:
The tribunal awarded interest at 20% per annum from the commencement of arbitration till payment, in accordance with the contract. The award of costs to Atlanta was upheld as they succeeded substantially in the reference.

Conclusion:
The court partially allowed the State's challenge, setting aside awards for reduced productivity, subsequent legislation, and royalty charges, while upholding the rest of the award. The challenges by Atlanta and the State regarding other claims were dismissed, confirming the tribunal's awards on various heads of compensation, interest, and costs.

 

 

 

 

Quick Updates:Latest Updates