Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2015 (5) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2015 (5) TMI 1219 - SC - Indian Laws


Issues Involved:
1. Object and Purpose of the 1976 Act
2. Necessity of Land Acquisition by the Authority
3. Delay and Laches
4. Compliance with National Capital Regional Planning Board Act, 1985
5. Invocation of Sections 17(1) and 17(4) of the Land Acquisition Act
6. Pre-notification and Post-notification Delay
7. Allegations of Mala Fide and Colourable Exercise of Power
8. Legality of Possession Taken Under Section 17(1)
9. Vesting of Land in the State
10. Lapse of Acquisition Under Section 11A
11. Non-payment of 80% Compensation Under Section 17(3A)
12. Waiver of Rights by Accepting Compensation
13. Acquiescence by Accepting Compensation
14. Impact of Third Party Rights and Developments
15. Effect of Previous Judgments Upholding Notifications
16. Conflicting Views of Division Benches
17. Relief Entitlement

Detailed Analysis:

1. Object and Purpose of the 1976 Act:
The High Court concluded that the primary objective of the U.P. Industrial Area Development Act, 1976 was not limited to industrial development but included residential and other purposes. The Authority's misconception that land must be acquired for development was criticized.

2. Necessity of Land Acquisition by the Authority:
The High Court noted that the Authority wrongly believed that land acquisition was compulsory for development under the 1976 Act, leading to excessive acquisition of fertile agricultural land.

3. Delay and Laches:
The High Court dismissed writ petitions filed with inordinate delay and laches, specifically those challenging notifications issued before 2000. However, it entertained petitions where landowners challenged the change in land use from industrial to residential, considering this a valid reason for delay.

4. Compliance with National Capital Regional Planning Board Act, 1985:
The High Court found that land could not be acquired without the Board's permission. However, it was noted that the necessary consent had been obtained in these cases, leaving the legal question open.

5. Invocation of Sections 17(1) and 17(4) of the Land Acquisition Act:
The High Court held that the invocation of urgency provisions under Sections 17(1) and 17(4), thereby dispensing with the right to file objections under Section 5A, was illegal and unwarranted.

6. Pre-notification and Post-notification Delay:
The High Court found that delays before and after the issuance of notification did not justify invoking urgency provisions.

7. Allegations of Mala Fide and Colourable Exercise of Power:
The High Court agreed with the landowners that the acquisition was arbitrary and a colourable exercise of power, as the land was later allotted to private builders for residential purposes.

8. Legality of Possession Taken Under Section 17(1):
The High Court found that possession taken under Section 17(1) was not in accordance with the law.

9. Vesting of Land in the State:
The High Court noted that once possession is taken under Section 17(1), the land vests in the State, and the challenge to the notifications cannot be entertained.

10. Lapse of Acquisition Under Section 11A:
The High Court did not find the acquisition to have lapsed under Section 11A, as the declaration of the award was within the stipulated time.

11. Non-payment of 80% Compensation Under Section 17(3A):
The High Court noted that non-payment of 80% compensation as required by Section 17(3A) was fatal to the acquisition proceedings.

12. Waiver of Rights by Accepting Compensation:
The High Court held that accepting compensation did not amount to waiving the right to challenge the acquisition.

13. Acquiescence by Accepting Compensation:
The High Court found that accepting compensation did not equate to acquiescence, and landowners could still challenge the acquisition.

14. Impact of Third Party Rights and Developments:
The High Court balanced equities by not quashing acquisitions where substantial development and third-party rights had been created, instead enhancing compensation and allotting developed land.

15. Effect of Previous Judgments Upholding Notifications:
The High Court acknowledged the impact of previous judgments but chose to provide relief based on the specific facts of the case.

16. Conflicting Views of Division Benches:
The High Court resolved conflicting views by referring the matter to a larger bench, which ultimately found the invocation of urgency provisions unjustified.

17. Relief Entitlement:
The High Court categorized relief into three compartments: dismissing delayed petitions, quashing notifications for undeveloped villages, and enhancing compensation and land allotment for others.

Supreme Court's Conclusion:
The Supreme Court affirmed the High Court's judgment, noting that the High Court's approach balanced equities and provided substantial justice. The Supreme Court emphasized that the directions given by the High Court were unique to the specific circumstances and should not be treated as a precedent. Appeals were disposed of in terms of the High Court's judgment, and the contempt petitions were also disposed of.

 

 

 

 

Quick Updates:Latest Updates