Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Income Tax Income Tax + AT Income Tax - 2018 (10) TMI AT This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2018 (10) TMI 1945 - AT - Income Tax


Issues Involved:
1. Deduction under Section 80IB(10) of the Income Tax Act.
2. Completion of the project within the stipulated time.
3. Reliance on the judgment of the Hon'ble Gujarat High Court in the case of Tarnetar Corporation.
4. Interpretation of the completion date as per Section 80IB(10)(a) of the Income Tax Act.
5. Auditor's report on project completion.
6. Validity of the order of the Commissioner of Income Tax (Appeals).

Detailed Analysis:

1. Deduction under Section 80IB(10) of the Income Tax Act:
The primary issue revolves around whether the assessee is entitled to a deduction under Section 80IB(10) of the Income Tax Act amounting to ?50,58,54,491/-. The Revenue contends that the assessee did not meet the critical condition of completing the project within five years as per the stipulated guidelines.

2. Completion of the Project within the Stipulated Time:
The Revenue argued that the assessee failed to complete the project within the stipulated five years, as the Building Use Certificate (BUC) for Towers 2, 5, and 7 was issued by the Surat Municipal Corporation on 28.09.2012, beyond the deadline of 31.03.2012. The CIT Departmental Representative (CIT-DR) emphasized that the completion date should be considered as the date when the completion certificate is issued by the local authority, which in this case was after the stipulated time.

3. Reliance on the Judgment of the Hon'ble Gujarat High Court in the Case of Tarnetar Corporation:
The CIT(A) allowed the deduction by relying on the judgment of the Hon'ble Gujarat High Court in the case of Tarnetar Corporation, where it was held that if the project was completed before the final date but the local authority granted the business use permission after such date for technical reasons, the assessee would still be entitled to the deduction. The Revenue, however, argued that this judgment was not applicable as the facts of the present case were different and that the decision of the Gujarat High Court was challenged before the Supreme Court.

4. Interpretation of the Completion Date as per Section 80IB(10)(a) of the Income Tax Act:
The CIT-DR argued that the date of completion should be taken as the date when the completion certificate is issued by the local authority. The CIT(A), however, held that the project was completed on 17.03.2012, and the application for the completion certificate was made on 23.03.2012, before the stipulated deadline. The CIT(A) concluded that minor deviations pointed out by the local authority should not vitiate the purpose of the deduction.

5. Auditor's Report on Project Completion:
The auditor's report in Form 10CCB indicated that Towers 2, 5, and 7 were completed after 31.03.2012. However, the CIT(A) noted that the completion certificate from the Government approved chartered engineers and other supporting documents indicated that the construction was completed on 17.03.2012, and the application for the BUC was made on 23.03.2012.

6. Validity of the Order of the Commissioner of Income Tax (Appeals):
The CIT(A) allowed the deduction by relying on the binding judgment of the Hon'ble Gujarat High Court and considering the factual evidence provided by the assessee. The Tribunal upheld the CIT(A)'s order, stating that the construction was completed within the stipulated time, and the delay in issuing the BUC by the local authority should not be attributed to the assessee. The Tribunal dismissed the Revenue's appeal, finding no merit in the grounds raised.

Conclusion:
The Tribunal concluded that the CIT(A) was correct in allowing the deduction under Section 80IB(10) of the Income Tax Act, as the project was completed within the stipulated time, and the delay in issuing the BUC by the local authority was not attributable to the assessee. The appeal of the Revenue was dismissed.

 

 

 

 

Quick Updates:Latest Updates