Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2022 (11) TMI SC This

  • Login
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2022 (11) TMI 1500 - SC - Indian Laws


Issues Involved:
1. Claim of escalation by the Contractor.
2. Applicability of the principle of res judicata.
3. Interpretation and application of Clause 3.11(A) of the contract.
4. Jurisdiction and scope of the High Court under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983.

Detailed Analysis:

1. Claim of Escalation by the Contractor:
The Contractor claimed escalation costs due to the transportation of sand from an alternative quarry after the originally allotted quarry was depleted. The contract initially included provisions for such scenarios under Clause 3.11(A), which stated that no separate payment for leads or lifts would be made unless a quarry change occurred due to circumstances beyond the Contractor's control, and only upon the written order of the Superintending Engineer.

2. Applicability of the Principle of Res Judicata:
The State argued that the claim was barred by res judicata, referencing a previous arbitral award dated 06.10.2007 that had rejected a similar claim. However, the Court found that the initial claim lacked factual basis and written approval from the Superintending Engineer, which were present in the current claim. Therefore, the principle of res judicata did not apply as the conditions and facts differed significantly between the two claims.

3. Interpretation and Application of Clause 3.11(A) of the Contract:
Clause 3.11(A) was pivotal in determining the escalation claim. The Court found that the conditions for escalation were met: the depletion of the original quarry was beyond the Contractor's control, and the Superintending Engineer had granted written permission for using an alternative quarry. The Executive Engineer's conditional permission, which attempted to deny escalation, was deemed beyond his scope as the clause did not allow for additional conditions once the primary conditions were met.

4. Jurisdiction and Scope of the High Court under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983:
The High Court's power under Section 19(2) was examined to determine if the Arbitral Tribunal had acted outside its jurisdiction or with material irregularity. The Court found no such errors or misconduct in the Arbitrator's proceedings. The High Court had appropriately refrained from interfering with the award, as there were no grounds under Section 19(2) to do so.

Conclusion:
The Supreme Court upheld the Arbitral Tribunal's award granting the Contractor's claim for escalation. The conditions under Clause 3.11(A) were satisfied, and the principle of res judicata did not apply. The High Court's decision to not interfere with the award was found to be within its jurisdiction, leading to the dismissal of the appeal. Parties were ordered to bear their own costs.

 

 

 

 

Quick Updates:Latest Updates