Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2016 (2) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2016 (2) TMI 1386 - HC - Indian Laws


Issues Involved:

1. Whether the contract in dispute is a "works contract" or a "concession agreement".
2. Whether the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 apply or the provisions under section 9 of the Arbitration and Conciliation Act, 1996 apply.

Issue-wise Detailed Analysis:

1. Nature of the Contract: Works Contract vs. Concession Agreement

The primary issue was to determine whether the contract in question was a "works contract" or a "concession agreement". The appellants argued that the agreement was a concession agreement, allowing them to collect tolls for a specified period as compensation for their investment and efforts in the project. They pointed out that the agreement included provisions typical of concession agreements, such as the right to collect tolls, maintain the facility, and transfer it back to the government after the concession period. The court noted that the agreement involved elements such as the creation of an escrow account, tripartite security arrangements, and the recovery of investment through toll collection, which aligned with the characteristics of a concession agreement. The court relied on the precedent set in Jabalpur Corridor (India) Pvt. Ltd. v. M.P. Road Development Corporation Ltd., which distinguished between a works contract and a concession agreement based on similar criteria. Consequently, the court concluded that the contract was indeed a concession agreement.

2. Applicable Legal Framework: 1983 Act vs. 1996 Act

The second issue was whether the dispute should be governed by the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 or the Arbitration and Conciliation Act, 1996. The respondents contended that the dispute fell under the purview of the 1983 Act, which deals with works contracts, and thus the application under section 9 of the 1996 Act was not applicable. They argued that the contract was a works contract, and disputes should be referred to the M.P. Arbitration Tribunal as per the 1983 Act. However, the court found that the contract was a concession agreement, and the provisions of the 1996 Act were applicable. The court emphasized that the agreement explicitly referred to arbitration under the 1996 Act in case of disputes. The court also noted that the 1996 Act expressly saves the provisions of the 1983 Adhiniyam in certain respects, but this did not apply in the current context as the contract was not a works contract. The court set aside the order of the 1st Additional District Judge, Dewas, which had dismissed the application under section 9 of the 1996 Act, and allowed the appellants to pursue their claims under the 1996 Act.

In conclusion, the court determined that the contract was a concession agreement and that the provisions of the Arbitration and Conciliation Act, 1996 were applicable, allowing the appellants to seek remedies under this Act. The appeal was allowed, and the impugned order was set aside, granting liberty to the appellants to move an appropriate application under the 1996 Act.

 

 

 

 

Quick Updates:Latest Updates