Article Section | |||||||||||
ONE SIDED CLAUSES IN AN AGREEMENT CONSTITUTES AN UNFAIR TRADE PRACTICE |
|||||||||||
|
|||||||||||
ONE SIDED CLAUSES IN AN AGREEMENT CONSTITUTES AN UNFAIR TRADE PRACTICE |
|||||||||||
|
|||||||||||
Builder service When a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2 (o) of the Consumer Protection Act. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service. Building contract There shall be definitely a contract made between the builder and purchaser containing all the provisions required to fulfill the requirements. The clauses of the agreements should be fair, reasonable and applicable to both parties equally. The clauses of the agreements shall not be a favor for one person and disfavor to another person. If there is a position like this it would amount to ‘unfair trade practice’ under the provisions of the Consumer Protection Act, 1986. This has been explained the case law discussed as below. Case law In ‘Pioneer Urban Land & Infrastructure Limited v. Govindan Raghavan [2019 (4) TMI 231 - SUPREME COURT]’ – Civil Appeal No. 12238 of 2018 – SC (decided on 02.04.2019) the Appellant – Builder launched a residential project by the name “Araya Complex” in Sector 62, Golf Course Extension Road, Gurugram. The Respondent – Flat Purchaser entered into an Apartment Buyer’s Agreement dated 08.05.2012 with the Appellant – Builder to purchase an apartment in the said project for a total sale consideration of ₹ 4,83,25,280/-. As per Clause 11.2 of the Agreement, the Appellant – Builder was to make all efforts to apply for the Occupancy Certificate within 39 months from the date of excavation, with a grace period of 180 days. The project was commenced on 04.06.2012. The Building is supposed apply for the Occupancy Certificate by 04.09.2015, or within a further grace period of 6 months i.e. by 04.03.2016, and offer possession of the flat to the Respondent – Flat Purchaser as per Clause 11.2 of the Agreement. The appellant failed to do so. Therefore the flat purchaser filed a consumer complaint before the National Consumer Disputes Redressal Commission (‘National Commission’ for short) on 27.01.2017 alleging deficiency of service on the part of the Appellant – Builder for failure to obtain the Occupancy Certificate, and hand over possession of the flat. In the complaint the flat purchaser prayed for the following-
The National Commission passed an ex-parte Interim Order restraining the Appellant – Builder from cancelling the allotment made in favor of the Respondent – Flat Purchaser during the pendency of the Consumer Case on 02.06.2017. The Appellant – Builder obtained the Occupancy Certificate on 23.07.2018, and issued a Possession Letter to the Respondent – Flat Purchaser on 28.08.2018 during the pendency of proceedings before National Commission. The appellant submitted before the National Commissioner that since the construction of the apartment was complete, and the Occupancy Certificate had since been obtained, the Respondent – Flat Purchaser must be directed to take possession of the apartment, instead of directing refund of the amount deposited. The flat purchaser expressed that he did not want to take the possession of the flat on account of three years delay in giving possession of the flat. In the meanwhile he has taken an alternative flat and he demanded the refund of the entire amount with interest along with compensation. The National Commission allowed the complaint holding that-
The Appellant – Builder was directed to refund ₹ 4,48,43,026/- i.e. the amount deposited by the Respondent – Flat Purchaser, along with Interest @10.7% S.I. p.a. towards compensation. The rate of Interest @10.7% S.I. p.a. was fixed in accordance with Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017. However, for the period when the Interim Order dated 06.02.2017 was in operation, which restrained the Appellant – Builder from cancelling the Respondent’s allotment, no Interest was awarded. The National Commission ordered payment of Interest from the date of each installment till 05.02.2017 and from the date of the Order passed by the Commission till the date on which the amount would be refunded. The appellant, being aggrieved against the order of National Commissioner, filed appeal before the Supreme Court under section 23 of the Consumer Protection Act, 1986. Before the Supreme Court the appellant pointed out the clauses of the agreement made between the appellant and the purchaser on 08.05.2012.
20. RIGHT OF CANCELLATION BY THE ALLOTTEE
The appellant further submitted that-
The respondent, the purchaser submitted the following before the Supreme Court-
The Supreme Court heard the submissions of both the parties. The Supreme Court observed that the Apartment Buyer’s Agreement dated 08.05.2012 reveals stark incongruities between the remedies available to both the parties. Clause 23.4 of the Agreement entitles the Appellant – Builder to serve a Termination Notice upon the Respondent – Flat Purchaser for breach of any contractual obligation. If the Respondent – Flat Purchaser fails to rectify the default within 30 days of the Termination Notice, then the Agreement automatically stands cancelled, and the Appellant – Builder has the right to forfeit the entire amount of Earnest Money towards liquidated damages. On the other hand, as Clause 11.5 (v) of the Agreement, if the Respondent – Flat Purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the Agreement thereafter, and shall be bound by the provisions of the Agreement. The Supreme Court held that-
The Supreme Court also rejected the submission made by the Appellant – Builder that the National Commission was not justified in awarding Interest @10.7% S.I. p.a. for the period commencing from the date of payment of each installment, till the date on which the amount was paid, excluding only the period during which the stay of cancellation of the allotment was in operation. The Supreme Court dismissed the appeal filed by the appellant since it did not find any grounds to interfere with the orders of the National Commission.
By: Mr. M. GOVINDARAJAN - April 10, 2019
|
|||||||||||
|
|||||||||||