Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + HC Companies Law - 2013 (9) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2013 (9) TMI 503 - HC - Companies Law


Issues Involved:
1. Breach of Contract
2. Risk Purchase Damages
3. Liquidated Damages
4. Extra Expenditure
5. Demurrage
6. Award of Interest and Costs

Detailed Analysis:

1. Breach of Contract:
The contract between AMCI Australia Pty Ltd. (later renamed VALE Australia Pty Ltd.) and Steel Authority of India Ltd. (SAIL) required the supply of One Million Metric Ton of Hard Coking Coal from July 2007 to June 2008. AMCI/VALE failed to supply the agreed quantity, citing delays in port expansion and other operational issues. By December 2007, only 256,469 MT of coal was supplied, and AMCI/VALE informed SAIL of their inability to fulfill the contract, advising SAIL to consider other sourcing options. The Arbitrator found AMCI/VALE in breach of contract for failing to supply the contracted quantity of coal.

2. Risk Purchase Damages:
SAIL claimed damages for non-supply of 753,461 MT coal, asserting that they had to procure the shortfall from other suppliers at higher prices. The Arbitrator awarded damages to SAIL, holding that AMCI/VALE had waived the requirement for a risk purchase notice by advising SAIL to consider other sourcing options. The Arbitrator's decision was based on the established international practice of long-term supply contracts and the evidence that SAIL had indeed procured additional coal from other suppliers to cover the shortfall.

3. Liquidated Damages:
SAIL initially claimed liquidated damages as per clause 8.1 of the contract, which allowed for damages equivalent to 1% of the price of the coal, subject to a maximum of 10%. However, SAIL later gave up this claim during arbitration proceedings. The Arbitrator did not award any liquidated damages, focusing instead on the actual damages incurred by SAIL due to the breach of contract.

4. Extra Expenditure:
SAIL claimed extra expenditure incurred to procure the deficit coal from alternate sources. The Arbitrator awarded damages based on the increased cost of coal procured from other suppliers, considering the evidence provided by SAIL regarding the additional quantities purchased and the higher prices paid.

5. Demurrage:
SAIL claimed unpaid demurrage charges related to the delayed shipment of coal. The Arbitrator awarded SAIL the claimed demurrage charges, finding that the delays were attributable to AMCI/VALE's failure to supply the coal as per the contract.

6. Award of Interest and Costs:
The Arbitrator awarded pre-award interest at the rate of 2.335364% per annum, based on the Libor rate, and legal costs incurred by SAIL. The Arbitrator consciously omitted post-award interest, which was later upheld by the Single Judge. The Division Bench found no merit in SAIL's appeal for post-award interest, agreeing with the Single Judge's interpretation that the Arbitrator had rejected the claim for post-award interest.

Conclusion:
The Division Bench dismissed the appeals filed by VALE and AMCI, upholding the Arbitrator's award of damages to SAIL. The Bench also dismissed SAIL's appeal for post-award interest, finding that the Arbitrator had correctly omitted it. The bank guarantees furnished by VALE/AMCI were ordered to be encashed after six weeks, allowing them time to seek further remedies before the Supreme Court.

 

 

 

 

Quick Updates:Latest Updates