Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2003 (9) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2003 (9) TMI 539 - SC - Indian Laws


Issues Involved:
1. Delay in completion of the contract.
2. Termination of the contract.
3. Claims and counter-claims by the appellant and the first respondent.
4. Misconduct by the arbitrator.
5. Jurisdiction of the District Judge and High Court in setting aside the award.

Detailed Analysis:

1. Delay in Completion of the Contract:
The appellant and the first respondent entered into a contract for constructing an auditorium complex, initially set for completion on 15-3-1981. Due to an increased scope of work, the contract was amended, extending the completion date to 31-12-1982. Despite this, the appellant terminated the contract on 28-2-1983, after the due completion date. The arbitrator awarded compensation to both parties, attributing delays to both. However, the District Judge found the appellant responsible for a 1654-day delay in accepting designs, which the arbitrator did not consider, thus vitiating that part of the award.

2. Termination of the Contract:
The appellant terminated the contract after its completion date without granting further extension. The District Judge and High Court found this termination unjustified, as the contract could not be terminated post the completion date. The arbitrator's decision to award compensation to the appellant for extra expenditures to complete the work was inconsistent with his finding that the appellant was responsible for delays.

3. Claims and Counter-claims:
The first respondent claimed Rs. 23,59,534.72, while the appellant claimed Rs. 90,58,167.42. The arbitrator awarded Rs. 14,31,463 to the first respondent and Rs. 33,95,000 to the appellant. The District Judge found the awards inconsistent, as the arbitrator awarded damages to the first respondent for delays caused by the appellant but also compensated the appellant for completing the work left by the respondent, which was contradictory.

4. Misconduct by the Arbitrator:
The District Judge held that the arbitrator committed misconduct by accepting calculation sheets from the appellant on the last hearing date without prior intimation to the first respondent. The arbitrator's inconsistent findings on who caused the breach of contract and his failure to consider relevant facts or reliance on irrelevant factors constituted legal misconduct.

5. Jurisdiction of the District Judge and High Court:
The appellant argued that the District Judge and High Court exceeded their jurisdiction by setting aside the award, asserting that the award was non-speaking. However, both courts found the award inconsistent and based on misconduct by the arbitrator. The High Court upheld the District Judge's decision, emphasizing that the arbitrator's inconsistent conclusions amounted to misconduct. The appellant's failure to challenge the award in favor of the first respondent rendered the finding of breach by the appellant final, operating as res judicata.

Conclusion:
The Supreme Court upheld the decisions of the District Judge and High Court, finding no legal infirmity. The arbitrator's inconsistent findings and failure to consider relevant facts constituted legal misconduct, justifying the setting aside of the award. The appeals were dismissed, affirming the lower courts' judgments.

 

 

 

 

Quick Updates:Latest Updates