Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2019 (4) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2019 (4) TMI 1927 - HC - Indian Laws


Issues Involved:
1. Misrepresentation and Fraud
2. Estimation and Guarantee of Energy Generation
3. Evidence and Findings of the Arbitral Tribunal
4. Contractual Obligations and Clauses Interpretation
5. Claims for Damages and Compensation
6. Procedural and Natural Justice Concerns

Detailed Analysis:

1. Misrepresentation and Fraud:
The Arbitral Tribunal found that the Respondent had committed fraudulent misrepresentation by providing false estimates of energy generation to induce the Claimant into entering the Supply Agreement. The Tribunal noted that the Respondent withheld crucial information and data, including the missing page 9 of the Supply Agreement, which contained the turbine-wise production estimates. The Tribunal concluded that the Respondent's actions amounted to fraud under Section 17 of the Indian Contract Act, 1872.

2. Estimation and Guarantee of Energy Generation:
The Tribunal interpreted Clauses 9.1 to 9.3 of the Supply Agreement and concluded that these clauses collectively implied a guarantee of energy generation. Despite the Respondent's argument that Clause 9.3 did not constitute a guarantee, the Tribunal held that the estimated average annual generation of 49.71 lakh KWh per WEG was a warranty. The Tribunal rejected the Respondent's claim that there was no guarantee provided.

3. Evidence and Findings of the Arbitral Tribunal:
The Tribunal considered extensive documentary and oral evidence from both parties. It found that the Claimant had relied on the Respondent's representations and that the Respondent had deliberately withheld crucial information. The Tribunal noted discrepancies in the Cash Flow Statement and other documents provided by the Respondent. The Tribunal also considered the evidence of expert witnesses and concluded that the Respondent's estimates were not genuine.

4. Contractual Obligations and Clauses Interpretation:
The Tribunal interpreted the contract to give business efficacy to the terms and ensure the intent of the parties was fulfilled. It held that Clause 9.1, which provided a specific estimate of energy generation, could not be rendered meaningless by Clause 9.3. The Tribunal applied principles of contract interpretation to conclude that the earlier clause would prevail over any conflicting later clause, ensuring the contract's purpose was achieved.

5. Claims for Damages and Compensation:
The Tribunal awarded damages to the Claimant for the difference between the estimated and actual energy generation. The Claimant had initially sought rescission of the contract but later pressed for damages under the second part of Section 19 of the Indian Contract Act, 1872, based on the ongoing contract. The Tribunal awarded compensation up to the date of the award but rejected the Claimant's claim for compensation for the entire 20-year period.

6. Procedural and Natural Justice Concerns:
The Respondent argued that the Tribunal had violated principles of natural justice by not giving it an opportunity to address the Claimant's alternate claim for damages. However, the Tribunal found that the Respondent had ample opportunity to address both claims during the arbitration proceedings. The Tribunal also rejected the Respondent's claim that the award was delayed, noting that the proceedings continued after the initial hearing for various reasons, including the substitution of the Claimant's name.

Conclusion:
The Tribunal's findings were based on a thorough examination of evidence and contractual provisions. The Tribunal's interpretation of the contract and its decision to award damages to the Claimant were upheld. The Tribunal's decision to reject the Claimant's claim for compensation for the entire 20-year period was also upheld, as the Claimant had not provided a basis for predicting long-term energy estimates. Both Arbitration Petitions were dismissed, and the award was upheld.

 

 

 

 

Quick Updates:Latest Updates