Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2022 (1) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2022 (1) TMI 1343 - SC - Indian Laws


Issues Involved:
- Unfair trade practice by the developer.
- Liability of the developer for interest on refunded amount.
- Compensation for delay in project completion.
- Legal implications of returning the pay order.
- Entitlement to interest on the refunded amount.

Issue-wise Detailed Analysis:

1. Unfair Trade Practice by the Developer:
The complainant alleged that the developer engaged in unfair trade practices by failing to complete the construction of the flat within the promised timeframe and subsequently canceling the allotment. The MRTP Commission and later the COMPAT found the developer guilty of unfair trade practices under Section 36-A (1) (i), (ii) & (ix) of the MRTP Act, concluding that the developer falsely represented the completion time of the project, which extended over a decade instead of the promised three years.

2. Liability of the Developer for Interest on Refunded Amount:
The core issue revolved around the developer’s liability to pay interest on the amount of ?4,53,750/- refunded to the complainant. Initially, the developer issued a pay order dated 30th April 2005, which was returned by the complainant. The developer argued that once the pay order was issued and the amount was debited from its account, it had fulfilled its obligation. The Supreme Court, referencing Order XXI Rule 1(4) and (5) of the CPC, ruled that the developer could not be held liable for interest after 30th April 2005, as the payment was effectively made when the pay order was issued.

3. Compensation for Delay in Project Completion:
The COMPAT awarded compensation to the complainant in the form of 15% compound interest per annum on the amount deposited from the date of each installment until 30th April 2005. This was upheld by the Supreme Court, which also directed the developer to pay the principal amount of ?4,53,750/- to the complainant’s legal representatives.

4. Legal Implications of Returning the Pay Order:
The complainant returned the pay order issued by the developer, which was then deposited with the MRTP Commission. The Supreme Court noted that the complainant did not take steps to ensure the amount was placed in an interest-bearing account. The court emphasized that the developer’s liability ceased once the pay order was issued and debited from its account, and the complainant’s failure to secure an order for interest-bearing deposit meant no further interest was payable by the developer.

5. Entitlement to Interest on the Refunded Amount:
The Supreme Court concluded that the complainant was not entitled to interest on the refunded amount after 30th April 2005. The court referenced the principle that once payment is made through a bank instrument, the liability for interest ceases. The Tribunal’s order directing the developer to pay further compensation in the form of compound interest was set aside, and the developer’s appeal was allowed.

Conclusion:
The Supreme Court allowed the developer’s appeal, setting aside the NCLAT’s order that directed further compensation in the form of compound interest. The complainant’s appeal for interest from 1993 to 2016 was dismissed. The court also suggested that judicial forums should frame guidelines to ensure amounts deposited with them are placed in interest-bearing accounts to avoid similar issues in the future.

 

 

 

 

Quick Updates:Latest Updates