Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2017 (2) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2017 (2) TMI 1546 - HC - Indian Laws


Issues Involved:
1. Delay in completion of construction work.
2. Responsibility for delay and damages.
3. Arbitration Award and its modification.
4. Quantification of escalation costs and damages.
5. Interest rates on awarded amounts.

Issue-wise Detailed Analysis:

1. Delay in completion of construction work:
The appellant, a Civil Engineer/Contractor, was entrusted with the construction of an Office of Conservator of Forest and quarters at Sirsi in 1989. The contract stipulated completion by 6.5.1992. The contractor failed to complete the work within the period, leading to the rescission of the contract by the respondents.

2. Responsibility for delay and damages:
The contractor attributed the delay to the Department, citing reasons such as change of site, modification of plans, and lack of water facilities. The Department refuted these claims, arguing that the delay was due to the contractor's failure to commence work on time. The Department contended that the change of site was minor and did not justify the delay.

3. Arbitration Award and its modification:
An Arbitrator awarded Rs. 14,68,239/- with 18% interest p.a. from 9.3.1994 till the date of payment, along with arbitration costs of Rs. 50,000/-. The respondents challenged this award under section 34 of the Arbitration & Conciliation Act, 1996. The Senior Civil Judge, Sirsi, modified the award to Rs. 3,71,564/- with 9% interest p.a. and reduced arbitration costs to Rs. 10,000/-. The contractor appealed against this modification.

4. Quantification of escalation costs and damages:
The Arbitrator awarded amounts for various claims, including losses due to idle labor and machinery, extra expenses, and revised rates beyond the stipulated period. The main dispute centered on claim No.7, which involved payment for escalated costs of work executed beyond the original time frame. The court found the Arbitrator's quantification of damages to be arbitrary and unsupported by material evidence, deeming it contrary to public policy. The court held that the delay was not exclusively due to the Department's default and that the contractor could have proceeded with the office building construction despite the site change for residential quarters.

5. Interest rates on awarded amounts:
The Arbitrator's interest rate of 18% p.a. was deemed excessive. The court referenced the Supreme Court's decision in 'MUKAND LTD. vs. HINDUSTAN PETROLEUM CORPORATION LIMITED,' which reduced post-decree interest rates. The court found the 9% interest rate awarded by the lower court to be reasonable, considering the long lapse of time and the totality of circumstances.

Conclusion:
The appeal was dismissed, upholding the lower court's modification of the Arbitration Award. The court found no infirmity or irregularity in the impugned judgment, concluding that the determination of damages and interest rates by the lower court was justifiable and supported by the available material evidence.

 

 

 

 

Quick Updates:Latest Updates